Starting in 1911, Great Northern Railway let a contract for grading of a new branchline running north from Bluestem through Davenport and down Hawk Creek Canyon to the Columbia River at Peach then turning north toward the mouth of the Spokane River at Fort Spokane. Just below Hawk Creek Falls a short distance from Peach a tunnel was to be bored through a sharp bend in Hawk Creek Canyon. By early 1912 the tunnel was well along when this tragedy took the life Peter Olsen, originally of Sweden.

The incident convinced the project engineers that the soil above the tunnel was too unstable and the would be tunnel was turned into a deep cut that still exists. But it would be all for naught. Starting around 1907, the US Department of the Interior started earmarking various valleys for future dam and reservoir projects. Wanting to head off costly relocations of facilities such as railroads, they informed the railroad seeking to build in those valleys of their intention to flood those same valleys. I'm still trying to determine when the Great Northern was informed of the department's intention to flood the Columbia River Valley, but it was about the time the grading was finishing up on the new branch line. GN decided to not lay track on the grade. Of course the construction of the dam wouldn't take place until the Public Works Administration of the Great Depression. But this project actually went through unlike so many of those planned projects of the USDI. Other planned projects that never came about were at the mouth of the Deschutes River in Oregon and one just east of Connell to be filled by a diverted Palouse River with the reservoir extending all the way to Kahlotus.

Spokesman Review article, Jan 29th, 1912. 


Map showing the tunnel location in relation to Hawk Creek Falls.



If it had completed as proposed, the branch would have crossed Hawk Creek on a tall bridge above the boat. The tunnel would have been just to the right of the bridge in this view.


The retaining wall holding up the roadbed for the GN branch above Hawk Creek Falls can be seen in this view.



Really, if it wasn't for all the trouble they had at that one spot, GN probably would have laid track on the branch.



2 comments:

Phil Krogh said...

I feel kinda stupid because I've looked at many photos of the falls and never noticed that wall!

SDP45 said...

I love new discoveries like this!

Don't feel like you're the only one this happens to.

Dan