COMPLETION OF GRAND COULEE DAM LEFT POWERHOUSE AND FOUNDATION FOR PUMPING PLANT

Schedule, Specifications, and Drawings

Columbia Basin Project, Washington

United States Department of The Interior
Bureau of Reclamation

Specifications No. 757

Bids will be received by the Bureau of Reclamation, at the Civic Building, Spokane, Washington, until 1:00p.m., December 10, 1937

Schedule

Page 4
Item 11 Excavation, common, for roads and railroad
1,500 cubic yards at $1.50 per cubic yard

Item 12 Excavation, rock, for roads and railroad
118,000 cubic yards at $2.00 per cubic yard

Page 5
Item 27 Laying ties and rails
750 track feet, at $1.70 per track foot

Item 28 Applying rail anchors
850 anchors, at $.20 per anchor

Item 29 Ballasting railroad track
600 cubic yards, at $3.00 per cubic yard



Page 13
Item 180 Transporting freight of all kinds on the construction railroad for the Government or its agents, other than the contractor, in carlots between delivery yard and Government siding at head of Grand Coulee
310 cars, at $55 per car

Page 14
Item 181 Transporting freight of all kinds on the construction railroad for the Government or its agents, other than the contractor, in less than carlots between delivery yard and Government siding at head of Grand Coulee
5,000 cwt, at $.30 per cwt

Item 182 Transporting freight of all kinds on the construction railroad for the Government or its agents, other than the contractor, in carlots between delivery yard and Government siding at head of Grand Coulee
100 cars, at $70 per car

Item 183 Transporting freight of all kinds on the construction railroad for the Government or its agents, other than the contractor, in less than carlots between delivery yard and Government siding at head of Grand Coulee
2,000 cwt, at $.30 per cwt

Item 184 Transporting freight of all kinds on the construction railroad for the Government or its agents, other than the contractor, in carlots between delivery yard and Government siding at head of Grand Coulee
1,000 tons, at $4 per ton

Total bid price for all 185 items: $34,442,224.00

Page 20
Special Conditions

18.
Rate of wages
Brakeman (railroad, standard gage road 30 miles long) $.90 per hour

Page 21
Rate of wages
Conductor, railroad (standard gage Government railroad, 30 miles long) $1.00 per hour
Fireman, railroad $.90 per hour

Page 22
Rate of wages
Locomotive engineer $1.35 per hour

Page 31
Materials

29.
Materials furnished by the Government
…All other materials furnished by the Government will be delivered to the contractor f.o.b. cars at Odair, Washington.



Page 33 and 34

32.
Storage of Materials
… The Government has constructed a siding on the Government construction railroad at the head of Grand Coulee, of sufficient length to provide for unloading and storing equipment to be installed by the Government and has installed a gantry crane of sufficient capacity to handle the heaviest pieces required. All additional sidings and spur tracks at the head of Grand Coulee, required for unloading and storing materials delivered to the contractor at Odair, Washington, shall be constructed by and at the expense of the contractor.

Page 43, 44, and 45

50.
Construction Railroad
A railroad for use in transporting construction materials to the dam site has been constructed by the Government, extending from its junction with the Northern Pacific Railway at Odair, Washington, to the dam site, a distance of about 30 miles, as shown on the location map. The railroad is standard gage, of substantial construction, and consists of a single track, with no siding, passing, or spur tracks, except for the delivery yard at Odair, one passing track at the head of Grand Coulee, a spur track to the gantry crane, side tracks at the cement unloading and blending plant, and a side track to the Government warehouse and storage yard. The railroad will be turned over to the contractor by a written order from the contracting officer, and upon the receipt of such written order, the contractor shall immediately accept the railroad and assume its operation and maintenance. The contractor shall construct at his own expense or purchase from the previous contractor, all additional siding, passing, spur, and switching tracks and wyes required for his operations, shall furnish and install, when and where directed by the contracting officer, a complete switch layout for a spur track to the field fabrication plant of the contractor for furnishing the penstocks and pump inlet pipes, and shall furnish all necessary rolling stock and other equipment require for the operation and maintenance of the railroad. The contractor shall operate and maintain the railroad and shall haul and handle all materials delivered to the contractor by the Government as provided in paragraph 29 for use in the construction of the dam, powerhouse, and foundation for the pumping plant, and the entire cost thereof shall by included in the prices bid in the schedule for the items of work in the performance of which the railroad is used. The engines used by the contractor shall not be heavier than 200 tons and carloads shall not be heavier than 300,000 pounds: Provided, That for infrequent loads, carloads heavier than 300,000 pounds may be transported subject to the specific approval of the contracting officer: Provided further, That all materials delivered in carload lots to the contractor by the Government may, at the option of the contractor, be hauled without charge over the railroad. In addition to the materials to be transported over the railroad as above specified, the contractor shall also transport in either direction, from the delivery yard at Odair to the Government siding or field fabricating plant at the head of Grand Coulee, to the siding at the Government warehouse, or to the dam, all materials of every kind and nature required to be transported for the Government or for other contractors or agents of the Government engaged on work on any part of the Columbia Basin project. Such additional transportation service shall be promptly and efficiently handled to the satisfaction of the contracting officer, and the contractor shall be held liable for any damage to material while in the care of the contractor during loading, transporting, and unloading. The rules and regulations under which such additional transportation service shall be furnished shall be subject to the approval of the contracting officer. Payment for such additional transportation service will be made at the unit prices bid under items 177 to 184, inclusive, of the schedule. The unit prices bid in the schedule for transporting materials for the Government or its agents, other than the contractor, shall include the cost of loading and unloading such materials and, in the case of materials required to be placed in the Government warehouse, shall include the cost of placing the materials in the warehouse as provided in paragraph 29, Provided, That all materials delivered to the plant for the field fabrication of penstocks and pump inlet pipes will be unloaded by the contractor for fabricating the penstocks, and pump inlet pipes: Provided further, That all completed sections of penstocks and pump inlet pipes delivered to the contractor for transportation to or installation in the dam will be placed on the cars by the penstock and pump inlet pipe contractor, but all blocking, bracing, and ties required for safe transportation of the pipe sections shall be furnished and placed by the contractor under these specifications. The unit of measurement for payment under items 181 and 181 will be one hundred pounds and under items 180 and 182 will be a car. In making payment to the contractor for any shipment in one car, the rate will be used which will result in the lower cost to the Government. The contractor will not be paid under items 177 to 184, inclusive, for transporting any materials and equipment which are furnished to the contractor by the Government for installation or use in the work to be done by the contractor under these specifications. The previous contractor has transported and placed in the warehouse or storage yard materials for installation in the work. For such materials which are installed by the contractor under these specifications, the Government will deduct from the unit price bid in the schedule for installing the materials, the cost of transportation over the construction railroad as determined from the unit prices bid under items 180 to 183, inclusive, of the schedule. All transportation service to be paid for under items 177 to 184, inclusive, of the schedule will be ordered in writing by the contracting officer, and the unit prices bid in the schedule shall include the cost of all rental, demurrage, or other charges for railroad equipment while in the contractor's possession and the cost of returning the empty cars to the railway company at the delivery yard at Odair. In the event of any dispute or doubt as to the payment to be made for any transportation or unloading service specified herein or as to the rules or regulations applicable thereto, the matter shall be submitted to the contracting officer, whose decision shall be final. Insofar as practicable and applicable, as determined by the contracting officer, the practices and regulations current with the Northern Pacific Railway Company will be used as a guide by the contracting officer in approving regulations and deciding questions regarding them or their application. The contractor shall install and maintain all necessary crossing and warning signs and will be held responsible for the safe and proper operation of the railroad. The joint section of the railroad, being the delivery yard at Odair and a portion of the main line of the Northern Pacific Railway at the delivery yard, will be used in common by the Government, the railway company, and the contractor for delivering cars and equipment from one party to the other, but the operation of the joint section will be under the direction and control of the railway company, and before making use of the joint section, the contractor shall agree, in writing, with the Government and the railway company, to observe, so far as applicable to the contractor, the terms and conditions of the agreement between the United States of America and the Northern Pacific Railway Company, copy of which may be examined in the office of the Bureau of Reclamation at Washington, D. C., Denver, Colorado, or Coulee Dam, Washington. All operations of the contractor in connection with the railroad shall be subject to the approval of the contracting officer. The contractor shall maintain the railroad in good operating condition for the entire period during which the construction railroad is being operated by the contractor. If, in the opinion of the contracting officer, the contractor does not at any time properly maintain the railroad or any part thereof, the Government reserves the right to do any work which, in the opinion of the contracting officer, is necessary for its proper repair, maintenance, or operation, and to charge the cost thereof to the contractor. Within 10 days after the date on which the railroad is turned over to the contractor, the contractor shall inaugurate regular train service at least twice each week until the railroad is returned to the Government. If, in the opinion of the contracting officer, the contractor fails at any time to provide proper transportation service as required, the Government reserves the right to assume complete control of the railroad, to take over any or all of the contractor's railroad equipment in use on the railroad, and to operate the railroad for the purpose required by the contract at the expense of the contractor. Upon the completion of the contract under these specifications, the contractor shall return the railroad to the Government in as good condition as when turned over to the contractor, reasonable wear and tear excepted. The Government reserves the right to operate its own trains or motor cars of any nature desired, for any period of time, over the railroad: Provided, That such operation of trains or motor cars will be arranged to interfere as little as practicable, as determined by the contracting officer, with the necessary work of the contractor, and the trains shall be dispatched by the contractor. Except as otherwise provided in this paragraph, the cost of all work described in this paragraph shall be included in the unit prices bid for the various items of work in the schedule in the performance of which the railroad is used.

Page 65, 66, and 67

Railroad

84.
Laying ties and rails
The extension of the railroad to the left powerhouse shall be constructed by the contractor. All ties, rails, angle bars, tie plates, spikes, bolts, and nut locks will be furnished by the Government as provided in paragraph 29. Ties shall be placed 16 to the 30-foot rail and 17 to the 33-foot rail. For shorter rails the spacing shall be in the proportion of 16 to a 30-foot rail. The ties shall be placed and maintained normal to the line of the rails, and the ends of the ties on one side of the track shall be lined parallel to the rail. Selected ties shall be used for curves of two degrees or more and at rail joints, as directed by the contracting officer. The heart side of ties shall be turned down except that where ties are not straight the bow side shall be up. Ties shall be adzed where necessary to obtain even rail bearing. The ties shall not be damaged by picks, shovels, or other tools or by over-spiking. Tie hooks or tongs shall be used instead of picks. The rails will be approximately 90-pound second-hand or relay rail. In unloading from the cars, the rails shall be skidded or otherwise carefully handled. All rails shall be laid with staggered joints. The joints on one side shall not vary more than 12 inches in either direction from the center of the opposite rail. Rails of less than standard length shall be used for curves, to bring the joints in proper position. Before being laid, all rails on curves of three degrees or more shall be curved by means of an approved rail bender. Relay rails shall be matched so that the worn portions will be on the same side of the rail and shall be laid with the worn portion on the inside or outside of the track as directed by the contracting officer. Rails shall be laid with the base of the rail true to the plane of the track. The rails shall not be driven into position with a hammer, maul, or any similar tool, but shall be moved with rail tongs or lining bars. The proper allowance for expansion and laying rail will be governed by the temperature of the rail, as determined by the contractor by means of a rail-laying thermometer. The proper allowance for expansion at joints shall be secured by using standard metal expansion shims. For 30-foot lengths of rail, the shims shall be omitted at every tenth joint. The rail- laying thermometer and expansion shims shall be furnished by the contractor and shall besubject to the approval of the contracting officer. To insure proper adjustment at joints, the rails shall be brought together, with expansion shim inserted, and carefully bolted and all bolts thoroughly tightened before spiking; after which the expansion shim shall be removed. Each joint shall be supported by two ties, with the spikes in the slots provided in the angle bars. Special care shall be taken in applying angle bars. The bolts in each angle bar shall be placed with two heads inside and two heads outside of the rail. A full set of bolts with nut locks shall be used at each joint and, where necessary, holes shall be drilled in the rails to accomplish this. The inside of each angle bar and that portion of the rail covered by the angle bar shall be given a brush coat of oil before the angle bar is placed. After the joint is completed and bolts fully tightened, the outside of the angle bar shall be given a brush coat of oil. The oil for this purpose will be furnished to the contractor as provided in paragraph 29, and the necessary brushes shall be furnished by the contractor. All nuts shall be tightened by using wrenches of proper sizes to fit the nuts and bolts. Wrenches for 7/8 inch bolts shall have a lever arm of 36 inches, and for 1-inch bolts the lever arm shall be 48 inches. Joints shall not be spiked in holes in slots until after all bolts are fully tightened. All ties shall be fully tie-plated. Care shall be taken to obtain accurate gage of track, uniform bearing of the plates on the ties, and true bearing of the rails on the plates. The plates shall be set with the entire face of the shoulder in contact with the base of the rail, and in no case shall the tie plate be set with the shoulder under the base of the rail. All rails shall be fully spiked, four spikes to each tie. On curves of three degrees or more, three spikes shall be used to each rail, the extra spike being placed on the inside of the rail. A track gage shall always be used when spiking track. The standard gage of 4 feet 8 1/2 inches shall be used on tangents and on curves up to and including eight degrees. For curves sharper than eight degrees, the gage shall be widened at the rate of one-sixteenth of an inch for each degree of curve above eight degrees. The rail shall be held against the gage with a bar while the spikes are being driven. Spikes shall be started vertically and square and shall be driven so that the face of the spike will come in contact with the base of the rail. Spikes shall not be straightened while being driven, and care shall be taken not to overdrive the spikes. Angle bars shall be spiked in the slots provided for this purpose. The outside spikes of both rails shall be near one edge of the tie, and the inside spikes shall be near the other edge. The inside and outside spikes shall be spaced as far apart as the face and character of the tie or tie plate will permit, but no spike shall be nearer than two inches from the edge of the tie. After the track is laid, it shall be brought to approximate alignment before any ballast is placed. Bolts shall be gone over and retightened at short intervals and after several trains have passed over the track and before final acceptance all bolts shall be gone over again and thoroughly tightened to the satisfaction of the contracting officer. Payment for laying ties and rails will be made at the unit price per track-foot bid therefor in the schedule and for the actual number of track feet of track laid, which unit price shall include the cost of unloading, hauling, and placing all ties, rails, angle bars, tie plates, spikes, bolts, and nut locks in accordance with the specifications. No payment will be made for temporary spurs or sidings constructed by the contractor for his own use to facilitate construction work.

85.
Rail anchors.
Rail anchors shall be applied where directed by the contracting officer and in the most approved manner for the particular type of anchor furnished. Rail anchors will be furnished to the contractor by the Government as provided in paragraph 29. Payment for applying rail anchors will be made at the unit price bid therefor in the schedule, which unit price shall include the cost of unloading, hauling, and applying the rail anchors.

86.
Ballasting railroad track.
The track for the extension of the railroad to the left powerhouse shall be ballasted as shown on the drawings or as directed by the contracting officer, and, in addition thereto, sections of the existing track near the spurs to the pumping plant shall be raised in grade by increasing the depth of ballast. All ballasting material shall be furnished by the contractor. Pit-run gravel from which all cobbles over three inches in size shall be raked may be used. The required amount of ballasting material shall be spread uniformly along the track, the track raised to the required height as indicated by grade stakes set by the contracting officer and the material solidly tamped under the ties. In raising track each jack shall be so regulated as to avoid bending angle bars or straining joints. After being raised, the track shall be aligned to conform strictly to the stakes set by the contracting officer. Each tie shall be tamped from 15 inches inside the rail to the end of the tie with a tamping bar, tamping pick, or shovel. The end of the tie outside of the rail shall be tamped first, and, if possible, a train or trains shall be allowed to pass over the track before tamping inside of the rail. No trains shall operate over the track until the tamping outside the ties has been completed. Rails that are damaged by reason of neglect on the part of the contractor to comply with these requirements shall be replaced at his expense. The center of the tie shall be tamped loosely with the blade of a shovel. After being settled by passage of a few trains, the final tamping and adjustment to line and grade shall be made and all ties shall be well tamped with tamping bars or tamping picks. During the ballasting operations, the elevation and sighting boards shall be in constant use. On curves, the outer rail shall be elevated, and the elevation tapered out on tangents at both ends, where necessary, as directed by the contracting officer. On all other portions of tangents, both rails shall be brought to the same level. After the ballasting is completed and the track is in perfect gage, surface, and line according to the stakes, the ballast shall be neatly trimmed to the section shown on the drawings or as directed by the, contracting officer and any surplus material shall be spread evenly along the slopes of the embankments outside of the roadbed section. Measurement for payment for ballasting will be made of the material in place after tamping and to the lines and grades shown on the drawings or as established by the contracting officer, and the space occupied by the ties will not be included. Payment for ballasting railroad track will be made at the unit price per cubic yard bid therefor in the schedule, which unit price shall include the cost of furnishing, hauling, placing, and tamping the required amount of material, raising and aligning the track, and surfacing as provided in this paragraph.