Images courtesy of the Coulee Pioneer Museum
In 1934, the MWAK Co. was the main contractor in the
construction of Grand Coulee Dam. Their job was to determine the logistics of
moving items to the various locations needed around the dam site. One of the
decisions made was to build a railroad bridge.
The bridge was to be located far enough downstream to be at
a reasonable height above the river, yet at a level that would allow ordinary
operation of the railroad.
The site chosen called for the construction of the track from
the beginning of the switchback to the right powerhouse along the sheer granite
rock wall on the northwest side of the model engineers’ town, through a 200-foot
granite rock tunnel, to the river shore, all along a maximum 5% grade.
The contractor announced that the bridge itself would be
constructed in fourteen days, and started on October 1, 1934. On that day, area
citizens would see a 7700-pound hammer for the pile-driver starting to embed
long wooden posts into the river bottom. No one at the time would believe the
contractor could construct such a span in two weeks, claiming that the news was
just a way for the project to grab headlines. In fact, scheduling was tight. Pile-drivers
were only scheduled to work on the bridge for ten days.
The short time span to finish the bridge was made to
coordinate with the finish of the railroad construction contract by David H.
Ryan from Odair to near the dam site, and the one to connect from there down
the hill by James Crick and Max Kuney.
Specifications of the bridge showed it as 100 feet above the
river, with a main span of about 600 feet. It had timber approaches 350 feet
long and 22 feet wide. It would be
comprised of 41 16-foot bents and be 656 feet long. Piles were driven 80 to 88
feet to bedrock.
Further talk of the project had the contractor completing it
within a week. It was said that carpenters would follow the pile-driver across
the river, thus when the last log was driven, it would only be a matter of
hours until the span would be open to traffic.
After the first week, the pile driver was only a third of
the way across the river. The associated grade down the hillside to the bridge was
about half complete at this time as well. As the bridge neared completion, work
on the associated railroad grade down the hill to it was stopped, as no railroad
shipments would be necessary until the summer of 1935.
After the bridge was opened, it was found that a neighboring
wooden pile trestle closer to the river level would be inundated by the rising
waters of the 1935 spring run-off. As such, the MWAK bridge was given safety
modifications for public use, which began on April 1, 1935.
By mid-June, reports said the laying of railroad track would
soon reach the bridge. A July report stated the entrance to Mason City from the
bridge was closed as work was started to widen the nearby bank for the railroad
grade, since the curve off the bridge was too sharp for the locomotives. Work
continued into August.
The speedy construction of the bridge was called into
question in October as the bridge was closed to allow the repairs of a pier,
which had slipped, causing the shifting of the deck. Doubts were raised at that
time if the bridge would ever be used by the railroad, as there remained very
little shipping from the west side to east side, and the east bank side was turning
out to be very unstable, causing concern that it could hold up the track with a
loaded train on it.
By January 1936, word from MWAK came that it did not plan to
use a railroad to bring material to the east side of the river, as originally
intended. With the heavy work along the back of the engineers’ town, the costly
tunnel through very hard granite, a nagging slide area near the tunnel, and
then the instability of the bank on the east side of the bridge, it was decided
that anything needed on the east side could be hauled by trucks.
By the end of the MWAK contract in 1938, it was thought the
bridge should be removed before the next contract was signed. There was some
speculation that the next contractor would remove it, provided MWAK made
arrangements to do so.
Instead, the new contractor continued to use the bridge
through 1941 for truck traffic. In 1943, the Bureau of Reclamation removed the
bridge, as it had become unsafe for further use, much of it salvaged for
further use elsewhere. In 1946, the Bureau removed the center pier, leaving the
other two for anchors in barge operation.
Most of the grade on the west side of the river, including
the tunnel, is still visible today. The approaches to the bridge are largely
gone and forgotten. At some point, the remaining piers were removed, leaving no
trace of this bridge today.
01 The bridge construction starts by building a pillar for
the pile driver.
02 The bridge is about half way done. Note how low the river
is.
03 The main structure is nearly done
04 The completed bridge. Note the gentle curve of the
railroad grade coming off the lower left of the bridge.
05 View of the bridge showing the east side bank that needed
to be removed to allow trains to pass. The soil was too unstable to allow
trains to pass here.
06 The completed bridge. Note the two pillars upstream that
show where the state highway bridge will be built.
07 The completed bride with the now complete state highway
bridge upstream. Note the railroad grade along the edge of town. The tunnel can
even be seen in this view.
08 After the plans to build a railroad to the bridge were
scrapped, parts of the grade were reused.
08-1 After the plans to build a railroad to the bridge were
scrapped, parts of the grade were reused.
09 Another view showing the tunnel near the left side of the
image along the cliff, and the grade down to the bridge.
10 Penstock load crossing the bridge. In the upper left of
the photo, you can see the tunnel.
11 This is how the contractor expected to use the bridge, by
running tracks over it and shuttling large loads to the east side of the river,
but it never came to be.
12 Disassembly of the bridge by Bureau forces.
13 Portions of the bridge were dynamited and then salvaged.
14 Portions of the bridge were dynamited and then salvaged.
15 Nothing remains today, but you can infer where the bridge
was by following the grade along the cliffs. Protection of the water edge by
the Bureau after the 1948 flood erased the remaining approaches on either side
of the river as the edges were regraded and then covered with large rock.
No comments:
Post a Comment