188 F.2d 277 (1951)
UNITED STATES
v.
NORTHERN PAC. RY. CO.
NORTHERN PAC. RY. CO.
v.
UNITED STATES.
Nos. 13895, 13896.
United States Court of Appeals Eighth Circuit.
March 22, 1951.
278
*278 M. L. Countryman, Jr., St. Paul, Minn., for Northern
Pac. Ry. Co.
C. U. Landrum, U. S. Atty., St. Paul, Minn., Spencer L.
Baird, Regional Counsel, Bureau of Reclamation, Amarillo, Tex., and A. B. Rood,
Attorney, Department of Justice, Washington, D. C., for the United States.
Before GARDNER, Chief Judge, and WOODROUGH and THOMAS,
Circuit Judges.
WOODROUGH, Circuit Judge.
This action was brought in the United States District Court
of Minnesota by the Northern Pacific Railway Company against the United States
of America under 28 U. S.C.A. § 41 (20), now 28 U.S.C.A. § 1346. (2), to
recover a balance claimed to be due the railroad for freight charges on six
shipments of cement from six points in the State of Washington to Odair,
Washington, from which point the cement was transported over a government-owned
railroad to the site of the Grand Coulee dam, where it was used in the
construction of the dam. Northern Pacific claimed that the amount
279
*279 which should have been paid for the shipments involved
in its action was the regular tariff rate, less the applicable land-grant
deductions; while the government claimed the rates applicable to the shipments
in question were lower rates granted by the Company to the Government pursuant
to a special contract entered into between the Railway Company and the
government under the Interstate Commerce Act, 49 U.S. C.A. § 22. The total
amount claimed by the Northern Pacific to be due on the six shipments was
$1,645.19. Adjudication of government liability for that amount, however, would
establish its obligation for similar claims of the Company amounting to some
$2,000,000. The government denied liability as charged and filed eight
counterclaims against the plaintiff in the amount of approximately $5,500,000.
On the trial of the case to the court without a jury, the court entered judgment
dismissing the action of the railroad and dismissing the counterclaims of the
government. Each of the parties appeal.
The facts, including controlling provisions of the contract
involved and documentary evidence, are set out at length in the opinion of the
District Court at 70 F. Supp. 836, but are epitomized for the purpose of this
opinion as follows: In 1933 the United States government set out to build a dam
and power plant at Grand Coulee, Washington. The initial appropriation voted by
Congress was $63,000,000. Limited by this amount, government engineers knew
that it would not be possible to build a dam large enough to fulfill all the
requirements of a proper dam for the location. Accordingly, plans were drawn
for a dam which could later be expanded into a larger dam. This "low"
dam would provide electric current, but would not be large enough to provide
any irrigation for the area. The fact that no irrigation would be provided made
the "low" dam unsatisfactory to everyone concerned, but it was decided
that nothing else could be done at the time.
On July 16, 1934, a contract was entered into between the
government and the Silas Mason Company, Walsh Construction Company, and the
Atkinson-Kier Company for "construction of Grand Coulee Dam and Power Plant,
as covered by Items 1 to 85, inclusive, of the Schedule of Specifications No.
570. * * *" Specification No. 570 provided for a low dam which would
provide hydro-electric power. Construction was started under this contract, but
continuing discussions were held concerning the advisibility of building a
"high" dam. Finally on June 5, 1935, by "Order for Changes No.
1" (which changes were authorized by the contract of July 16, 1934,
between the government and the Mason-Walsh-Atkinson Companies) the design was
changed, and the structure which was built was a foundation structure adapted
to economical construction of the "high" dam upon it. Subsequently,
the Mason-Walsh-Atkinson contract was terminated by "Change Order No.
2" on March 21, 1938, by which time further funds had been appropriated by
Congress and the work proceeded to completion of the "high" dam under
a contract dated February 7, 1938, between the government and Consolidated
Builders, Inc.
Solution of the transportation problem was of course one of
the first tasks of the government. After much discussion of various means,
methods, and routes of transportation, the government decided that the best
solution was to build a branch line railroad itself and to enter into a
contract under the Interstate Commerce Act, 49 U. S.C.A. § 22, with the
Northern Pacific Railway Company for the transportation of cement and other
materials. After many negotiations, a preliminary draft of a contract was drawn
which the Railway Company found acceptable on August 10, 1934, and which the
government approved on November 12, 1934. Further revision was then asked by
the Company, and finally a contract was drawn acceptable to both parties. This
formal contract was dated November 19, 1934, but was actually signed by the
Company on March 4, 1935, and by the government on July 17, 1935. By the terms
of this contract, the government was to build a railroad from Odair,
Washington, to the site of the dam, and the Company was to transport cement and
other materials at specified rates.
280
*280 In this contract, Section 12 provided: "The
following maximum rates, in cents per hundredweight, are hereby established by
the Company on cement moving over existing rail routes in cars loaded to
maximum capacity from certain points, as herein listed, in the State of
Washington to Odair, Washington, on Government bills-of-lading, for use in the
construction of the Grand Coulee dam and power plant: * *."
The suit of the railroad was based on the claim that said
contract was not applicable to the shipments of cement involved in the action
because those shipments were used in construction of the "high" dam
that was actually constructed. It alleged that the contract between Northern
Pacific and the government (including Section 12 above) provided a contract
rate only for the transportation of cement required for a so-called
"low" dam, as proposed in the contract of July 16, 1934, between the
government and the Mason-Walsh-Atkinson Companies. The government on the other
hand contended that the contract entered into with Northern Pacific provided
for the transportation of all the cement needed for building the Grand Coulee
dam and power plant in its finished form, or in other words, the "high"
dam as completed under the contract between the government and Consolidated
Builders, Inc. The trial court's ruling and judgment sustained the government's
contention and we consider first the appeal of the Railway Company asserting
error in the judgment dismissing the railroad's action.
It is evident from the record that the dispute in that
action turns upon the meaning to be ascribed to the words "Grand Coulee
dam and power plant" as used in the contract. Both parties contended, and
contend here, that the entire contract is not ambiguous, but each party claims
the phrase used in the contract means a different thing. The trial court
recognized that "Grand Coulee dam and power plant" had a very
definite meaning as generally used, but in view of the varying constructions
contended for, the court heard extrinsic evidence to explain the term in
dispute as used in the contract.
On consideration of the extrinsic evidence adduced before
it, the trial court held that the contract was ambiguous, and that it should be
judicially construed. The question as to whether an ambiguity exists in a
contract is to be determined by the court as a matter of law. 17 C.J.S.,
Contracts § 617; Whiting Stoker Company v. Chicago Stoker Company, 7 Cir., 171
F.2d 248; Golden Gate Bridge & Highway District of California v. United
States, 9 Cir., 125 F.2d 872. The phrase in question would ordinarily have only
one definite meaning — that contended for by the government. However, in view
of all the facts — the manner in which the construction contracts were awarded
by the government, the supplementing of the first contract by another, the long
course of negotiations between the railroad company and the government
concerning transportation — the court logically concluded that the attendant circumstances
gave rise to such indefiniteness of designation of the project as to render the
contract ambiguous.
When it is once established that the contract is ambiguous
then the meaning of its terms is a matter of fact to be determined in the same
manner as other questions of fact. Floyd v. Ring Construction Corporation, 8
Cir., 165 F.2d 125, 129, and cases there cited. In the present case, the court,
having properly determined that the contract was ambiguous, heard extrinsic
evidence for the purpose of clarifying the uncertain term. After considering
this evidence the trial court found that "when the contract was executed
by the plaintiff in March and the defendant in July, 1935, with full knowledge
that the high dam was then being constructed, manifestly both parties accepted
Grand Coulee dam and power plant to mean the high dam."
This finding of fact is amply supported by the evidence and
must be sustained in this court on this review. The court's finding that at the
time of making the contract the parties intended to cover and fix a rate for
transportation of cement for the entire construction designated "Grand
Coulee dam and power plant", i.e. the "high" dam, is conclusive
of the dispute as to the rate applicable to the shipments included in
281
*281 the railroad's action. It precluded recovery by the
Company in the action. We think the provisions of Section 20 and Section 12 of
the contract as construed by the trial court present no such conflict as to
require a contrary conclusion. The trial court's ruling to that effect was
without error.
The appeal by the railroad presents no error in the judgment
dismissing its case and that part of the judgment is affirmed.
II.
We turn to the government's appeal from the part of the
judgment which dismisses the government's counterclaims.
The counterclaims of the government against the railroad
were based on allegations that the Company induced the government to execute
the contract fixing excessively high and unjust transportation rates on cement
and materials for the Grand Coulee dam and power plant by means of fraud and
deceit.
In order to defeat the claim asserted by the railroad to the
effect that no valid contract between the parties fixed rates for the
transportation for which the railroad sued, and that the regular tariff rates
with land grant deductions controlled, the government had insisted that the
contract fixed the rates and that the contract was controlling and valid. The
court, as stated, found the contract to be subsisting throughout the work of construction,
applicable to shipments for use in the construction, and valid, and therefore
it dismissed the plaintiff's action.
But in its counterclaim the government took the position
that when the Northern Pacific first sought the business of transporting the
cement and materials for the Grand Coulee project the only line which the
Company had available from the west coast to Odair, Washington, was a long,
circuitous route covering an average of 440 miles from the six cities named in
the contract to Odair. See map in the opinion of the District Court at 70
F.Supp. 844. Other railroads, especially the Great Northern, had more direct
routes which would serve the same places from the coast to within a short
distance of the dam site at an average haul of 235 miles. In order for these
other lines to be utilized in getting supplies to Odair, and thence to Grand
Coulee, they would have to go into the city of Adrian, Washington, from the
west over their own lines and thence north to Odair (a distance of about 21 miles)
over the line of Northern Pacific. The government alleged that the Company
representatives told the government representatives that Adrian could not be
"opened up" to the other railroads, and that if the Northern Pacific
got the hauling contract, the cement and materials would have to be hauled over
the long circuitous line of that Company. As a matter of fact, after Northern
Pacific had been awarded the contract, an agreement was entered into between
Great Northern and Northern Pacific and the cement was actually transported
over the shorter lines through Adrian. The government contended that the
Company knew at all times that this shorter route would be employed, but that
the Company made the representations that the longer route would have to be used
in order to obtain an excessively high and unjust contract rate from the
government.
The government also claimed that the representatives of the
railroad had figured out and knew the correct land grant deductions applicable
to the regular tariff rates on the cement shipments but that the government
representatives had mistakenly figured the deductions too low. That the
railroad representatives purposely and wrongfully failed to disclose the
mistake of the government agents in this matter.
Although the trial court found that the government agents
had made a mistake in their computations of the land-grant deductions, it was
clear that the contract rates were not related in any way to the deduction
figures, and the mistake as to such figures in no wise affected the validity
and binding effect of the contract.
The government contended that the alleged misrepresentations
and alleged wrongful failure to disclose constituted fraud. It contended that
on account of such fraud the court should order a reduction in the contract
rate proportionate with the difference between the length of haul which plaintiff's
agent represented would
282
*282 have to be made and the length of haul as it actually
was. The Grand Coulee project was almost completed when the counterclaims were
set up and the freight charges had been paid in accordance with the contract
through the years of construction. The counterclaims sought a refund of part of
the payments made by the government, as well as other specified items of
alleged damage.
The evidence as to the conferences, correspondence, and
circumstances connected with the negotiations for, the formulation, agreement
upon, and execution of the contract in this case was voluminous and was
carefully analyzed and considered by the trial court. The court concluded there
was nothing to indicate that there were fiduciary relations between the parties
to the contract, but on the contrary, the participating agents were
intelligent, experienced men of affairs, dealing at arm's length with each
other. Each side had much data on all subjects considered, and had means
available to inform itself on any matter relevant to the contract. It was not a
situation where either party was dependent upon or had a right to rely upon the
other party for information as to any material matter. The court did not make a
finding sustaining the government's charge that a railroad agent had
represented that the materials would have to be hauled over the long route if
the contract were made with the plaintiff Northern Pacific. Nor was there
evidence to support a finding that the railroad agent referred to (Mr. Clark,
officer in charge of traffic) had made any false statements in the negotiations
for the rate contract. No "gateway" through Adrian had been opened at
the time of the negotiations but it was opened subsequently through contract
entered into between the railroads. Such contract was on terms advantageous to
the Northern Pacific because that railroad had the contract for the business
with the government. The court held specifically that the written contract
between the government and Northern Pacific fully and accurately expressed the
agreement made by the parties, that fraud was not a basis for any counterclaim
by the government, and that the contract was not vitiated by fraud.
It is clear from the record that in the trial court the
government took the position that it was entitled to obtain the money judgment
against the plaintiff which it sought in its counterclaim on account of the
alleged fraud of the railroad either through rescission of the contract that
had been entered into and almost entirely executed, or through a reformation
thereof, and the court on full consideration concluded none of such remedies
was open to the government. We find no error in that conclusion, or the
reasoning in support of it, and find no merit in the contentions presented
against it here.
But on this appeal it is strenuously urged for the
government that the alleged fraud of the Company gave rise to a right of action
in the government for damages for deceit, and reversal is sought for the
refusal of the trial court to award judgment for the government on that theory.
The effort has been to assimilate the government's case here to the situation
presented in the old case of United States v. Barlow, 132 U.S. 271, 10 S.Ct.
77, 33 L.Ed. 346. In that case, the United States brought a statutory action
against Barlow, a sub-contractor on a mail-hauling contract, for recovery of
sums paid Barlow due to a mistake of fact on the part of the government. This
mistake of fact was occasioned by the misrepresentation that additional men and
horses would be needed if Barlow was to be able to provide speeded-up service
over a new mail route. Barlow had calculated the time necessary on the new
route on the basis of the extremely slow miles-per-hour rate at which the mail
had been carried over the old slow and difficult route. The mistake or
misrepresentation that Barlow made was readily apparent, but the government
paid him the money demanded for more men and horses for the speedier service.
It was admitted that the additional men and horses were never used. The Supreme
Court held that the government was entitled to recover the sums paid for the
men and horses not used. The argument is that there was a similar situation and
a similar right to recovery on the part of the government in the case at bar.
283
*283 This case is readily distinguishable from the Barlow
case. In that case, the amounts paid by the government were determined on the
basis of Barlow's costs in performing the work. These costs were misrepresented
to be higher than they actually were. But there is no claim here that the rates
specified in the contract were related to or made dependent upon costs or
disbursements to be incurred by the Northern Pacific. The government agreed to
pay the rates and it imposed no restriction upon the Company as to which lines
of railroad should be used in the transportation. What was considered and
discussed was possible trucking from Great Northern points, possible extension
of the government railroad to connect with the Great Northern, the possible
construction of a cement mill at the dam site, and precedent established by the
Union Pacific's 20¢ rate for a similar haul over a distance comparable with the
short haul available in this case in connection with the Boulder Dam project.
The evidence shows that the contracts which the Northern Pacific made with the
Great Northern and the Milwaukee accorded a large percentage of the proceeds of
the hauling to the Northern Pacific in view of the small percentage of the haul
actually made on Northern Pacific tracks. On account of that fact the trial
court did at one place in its opinion refer to the contract as a
"bonanza" for the Northern Pacific. But the contracts the railroads
made between themselves are not within the issues of this case. The government
entered into the contract freely and voluntarily with means and opportunity to
be fully informed at the time and throughout the period of its execution. The
trial court made no finding that the contract rate was based on the longer
mileage, and an examination of the record shows that no such finding could have
been made. The rate finally agreed on in the contract compares favorably with
rates contemporaneously allowed the Union Pacific in the Boulder Dam project,
and it appears that at the time that was a deciding factor.
It is therefore apparent that the alleged misrepresentations
as to the mileage of haul could not afford any basis for an action in tort for
deceit. To afford a basis for such an action, the alleged misrepresentation
must have been a substantial factor in causing the defrauded party to act to
his detriment. It "must have had such relation to the transaction in hand
as to operate as an inducement to the action or omission of the complaining
party, and it must have been relied on by him." The complaining party
"must have used due diligence to discover for himself the truth or falsity
of the representation, or the relations of the parties to each other or the
location or character of the subject-matter of the transaction must have been
such as to excuse investigation and to justify his reliance upon the assertion
of the other." Roosevelt v. Missouri State Life Insurance Company, 8 Cir.,
78 F.2d 752, 757. The evidence does not bring this case within the applicable
principles.
Here, the rates agreed upon and specified in the contract
were not related to or based upon the mileage of the haul, but were to be paid
without regard to the route or distance of transportation. The railroad was
left entirely free to contract with other railroads whose hauls would be
shorter and it was within its rights in making such contracts.
It may be stated that the government did not present to the
trial court the theory of the case which it has most strenuously contended for
here. In the trial court the counterclaims were not presented as actions in
tort for damages for deceit. The government did not plead or claim a cause of
action for damages in tort for deceit. As stated, it sought recovery by means
of an accounting after a reformation, rescission, or modification of the
contract; and the grounds for such reformation, rescission, or modification
were the alleged misrepresentions of the Company. But we are mindful that
"in all dealings with the government, contractors and agents alike are
under obligation to deal strictly within the limits of the statutes and with
absolute honesty." "* * * the doctrines of fraud, unconscionable
dealing and unjust enrichment are to be strictly applied to insure fair and
honest dealing between the government and its citizens." Muschany v. United
States, 324 U.S. 49, 59, 65 S.Ct. 442, 448, 89 L.Ed.
284
*284 744. We have therefore considered whether a case was
made out for the government on any theory and we hold there was not.
Freight Other Than Cement.
In the contract here involved, in Section 12 after the
provisions for transportation of cement, there was the following further
provision: "On the balance of the items of materials, supplies and
equipment to be used in the construction of the Grand Coulee dam and power
plant and moving on Government bills-of-lading, the established commercial
freight rates over existing routes, less land-grant deductions, shall apply,
with the following exceptions: * *."
It is the contention of the government that this provision
gave the government a special rate for such materials — that is, the rate then
existing, and not merely the commercial rate which other shippers paid at the
time of the particular shipment billed. There were substantial raises in the
commercial rates from the time the contract was made to the time of the last
shipment made under the contract.
In construing this provision, the trial court held that it
merely gave the government the right to ship the other materials and to be
billed at the regular tariff rate less the applicable land-grant deduction.
With this conclusion we are in accord. It is the contention of the government
that if this construction is adopted, the provision in the contract is
meaningless. Such is not the case. Immediately preceding this clause is one
granting the government a special rate on cement. This clause was then put in
to show that the government was not to get a special rate on other materials.
Cement Shipments From Trident, Montana, and Portland, Oregon
— two points not named in the contract.
As the construction work proceeded, the rate of pouring of
cement exceeded all expectations. Consequently, it became apparent that the
cement mills in the six cities named in the contract could not produce and ship
sufficient cement to meet the building contractors' requirements. Negotiations
were then begun by the government with cement mills in the cities of Trident,
Montana, and Portland, Oregon, and shipments of cement were made from those two
cities.
The government paid for these shipments at the regular
tariff rates less the applicable land-grant deductions. Now in its counterclaim
the government contends that a special rate should have been applied to such
shipments, and that the government has therefore overpaid the Company to the
extent of the difference between the regular tariff rate less land-grant
deductions and the special rate, which the government claims should be an
"equitable rate". It is the contention of the government that when
the contract between Northern Pacific and the government was entered into, it
was the intention of both parties that the government should have an
"equitable rate" on all shipments of cement to the dam.
As a means of recovering these alleged overpayments the
government seeks reformation of the contract with Northern Pacific so as to
make it include special rates from the two cities named. As a basis for this
proposed reformation, it is claimed that there has been a mutual mistake in
omission of cities other than the six named in the contract. The Company denies
that there was any mistake on its part, and the terms of the contract, which
sets out with particularity the six cities and the rates applicable to cement
shipments from each, bear out the railroad's position. Further, the trial court
found "there is no ground for reformation because the written contract
fully and accurately expressed the agreement made by the parties." In the
face of this, the government can hardly be said to have sustained the burden of
proof resting on the party alleging the mistake and seeking reformation to
"show exactly in what it [the mistake] consists and the correction that
should be made. * * * The mistake must be mutual, and common to both parties to
the instrument. It must appear that both have done what neither intended."
Moffett, Hodgkins, & Clarke Company v. Rochester, 178 U.S. 373, 385, 20 S.
Ct. 957, 961, 44 L.Ed. 1108. See also Maryland
285
*285 Casualty Company v. United States, 8 Cir., 169 F.2d
102, 111, and cases there cited.
Other than this, there is a clause in the contract itself
which refutes the government's claim of a mutual mistake in omitting other
cities. The last sentence of Section 12 of the contract states: "If the
necessity arises for revising said rates or for the fixing of rates on
additional items or from additional points, adjustments will be made in the
established rates or such new rates will be made as may be agreed to by the
authorized representatives of the Company and the United States." Thus the
parties to the contract expressly provided for the exact situation which arose
— "the fixing of rates * * * from additional points." Since the
government chose not to negotiate new rates, and paid, without protest at the
time, the regular tariff rate less land-grant deductions, the government must
be held to have consented to have that rate be the contract rate from the two
additional cities.
In the absence of a negotiated special rate from Trident and
Portland, the government has no grounds for its counterclaim for overpayment on
cement shipments from those two cities.
Conclusion.
On consideration of the whole record the conclusion of the
court is that the judgment appealed from is without error and it is in all
respects affirmed.
No comments:
Post a Comment