Monday, August 25, 2008

The Wenatchee Southern--The ICC Viewpoint-Part 2

FINANCE DOCKET No. 2172

CONSTRUCTION OF LINE BY WENATCHEE SOUTHERN RY. CO.

Approved December 2, 1924

ORDER

It appearing, That on July 14, 1924, the commission issued its report, and certificate and order, in the above-entitled proceeding, in which certificate and order it was provided that construction of the line of railroad therein authorized should be commenced on or before January 1, 1925;

It further appearing, That, for good cause shown, the Wenatchee Southern Railway Company will be unable to commence the construction of said line of railroad within the period prescribed in said certificate and order, and has requested that the time limit therein fixed for commencement of such construction be extended to July 1, 1925:

It is ordered, That the time prescribed in said certificate and order within which the Wenatchee Southern Railway Company may commence the construction of said line of railroad be, and it is hereby, extended to July 1, 1925.

No comments: