The Wenatchee Southern--The ICC Viewpoint--Part 3

FINANCE DOCKET No. 2172

CONSTRUCTION OF LINE BY WENATCHEE SOUTHERN RY. CO.

Approved July 1, 1925

ORDER

It appearing, That on July 14, 1924, the commission issued its report, certificate, and order in the above-entitled proceeding, in which certificate and order it was provided that construction of the line of railroad therein authorized should be commenced on or before January 1, 1925.

It further appearing, That by order entered December 2, 1924, the time for commencing construction of said line of railroad was extended to July 1, 1925.

It further appearing, That, for good cause shown, the Wenatchee Southern Railway Company will be unable to commence the construction of said line of railroad within the period prescribed in said certificate and order, as extended, and has requested that the time limit for the commencement of such construction be further extended to January 1, 1926:

It is ordered, That the time prescribed in said certificate and order within which the Wenatchee Southern Railway Company may commence the construction of said line of railroad be, and it is hereby, further extended to January 1, 1926.