Images courtesy of the Coulee Pioneer Museum.
Cement
Handling at Grand Coulee Dam
While many people know that a lot of cement was used in the construction of Grand Coulee Dam, what is not known is how it was handled.
Unlike
bulk loading today, which uses hopper-bottom vehicles to allow the
cement to pour from the bottom, such technology was not common in the
1930s. Therefore, all of the cement was loaded into boxcars. Those
boxcars had a solid flat floor, and the only way to load and unload
was the door in the middle of each side of the car.
Fortunately,
with a project the size of Grand Coulee Dam, a technology had already
been perfected in unloading bulk cement from boxcars, and had been
proven in use during construction of Hoover Dam: the Fuller-Kinyon
screw pump.
This
screw pump was first envisioned by Alonzo Kinyon of the Fuller-Lehigh
company and built in 1918 as a safe way to handle pulverized fuels.
Kinyon discovered that dry pulverized materials assume a flowing,
liquid-like consistency when properly mixed with air. In this
fluidized condition, pulverized materials can move through a pipeline
as a relatively dense column and at low velocity. He was looking for
a better way to move pulverized coal, which was used as a fuel in
boiler furnaces. Companies had used large fans to blow the dust
through ducts, which created an explosion risk. Open conveyor belts
were no better, since the dust they gave off could also spark an
explosion. Area cement producers who were familiar with his product
were quick to adopt his technology as a very practical means for
easily moving the powdered cement. He was awarded a patent in 1925
for the pump.
Cement
for Grand Coulee Dam was obtained from five cement mills located
within the State of Washington. It was transported in bulk via
boxcars which held about 266 barrels of cement, with one barrel
equaling 300 lbs of cement. Boxcars were pulled up an incline to the
unloading area. Unloading from there was accomplished by four
Fuller-Kinyon pumps, each of which resembled a large vacuum. A
horizontal, rotating disk, running close to the floor of the car,
caused the cement to flow into the open end of a small chamber
containing a motor-driven screw, which forced the cement into a
five-inch pipe. Near the junction of the screw casing and the
delivery pipe, compressed air was admitted. The cement was then
forced through hose and piping into the silos. While earlier pumps
were controlled by levers, later pumps at the dam were operated by a
wand with mercury-filled switches in it. The operator could control
the operation of all five of the motors on the pump, moving it in any
direction or changing the rate of feed by a mere tilt of the hand.
Two
men were used to unload each car. One handled the controls of the
pump and the other helped to clean up the car as the machine moved
along.
Each
pump could operate at 600 barrels, or 180,000 lbs per hour, and the
record for unloading was set on November 1, 1939 when one pump
emptied 130 boxcars of cement in one day, or a little over 10 million
pounds.
Storage
of the cement was in eight 5,000-barrel steel silos along the tracks,
which equaled about 12 million pounds of cement. In addition to the
silos were two 5,000-barrel silos for storing the blended product
from the mills.
From
the silos, screw conveyors brought the material into the two
5,000-barrel blending silos in the proper ratio. Underneath those
silos were two compression chambers, each with a capacity of 50
barrels or 15,000 lbs of cement. Compressed air was used to blow the
cement from the chambers via an 11-inch pipeline to the mixing
plants. The pipe line running to the west side mixing plant was 2,000
feet in length, while the line to the east side was 6,000 feet long.
There the cement was mixed into concrete and placed as needed
throughout the dam site.
Movement
of the empty boxcars was accomplished by gravity. The brakes were
released and the empty cars were rolled down the inclined track, past
an automatic track switch, and up to the end of a steep grade. From
there, they again rolled back and onto the main track, where they
were moved away by a locomotive, to be returned to the cement mills
for refilling.
No comments:
Post a Comment