NORTHERN PAC. RY. CO.
v.
UNITED STATES.
Civil Action No. 129.
District Court, D. Minnesota, Third Division.
December 30, 1946.
*837 *838 *839 L. B. daPonte and M. L. Countryman, Jr., both of St. Paul, Minn., for plaintiff.
Victor E. Anderson, U. S. Atty., and John W. Graff, Asst. U. S. 
Atty., both of St. Paul, Minn., and Spencer L. Baird, Dist. Counsel for 
Bureau of Reclamation, of Amarillo, Tex., for defendant.
BELL, District Judge.
The Case.
The Northern Pacific Railway Company commenced this suit against the 
United States under the act of Congress of March 3, 1887, 28 U.S.C.A. § 
41(20), commonly known as the Tucker Act, to recover a balance claimed 
due for freight charges on shipments of cement from six points 
*840
 in the state of Washington to Odair, Washington. This action is brought
 by the Northern Pacific Railway Company as a delivering carrier. The 
Great Northern Railway Company and the Chicago, Milwaukee, St. Paul 
& Pacific Railway Company as connecting carriers are interested 
parties, although not joined as plaintiffs. If recovery is had, these 
carriers will share therein in accordance with the division agreements 
between them.
If this suit involved only the claims for unpaid balances on six 
freight shipments, the problem under the circumstances would be quite 
sufficient, but it is to establish a precedent for claims of the 
plaintiff aggregating approximately $2,000,000. Moreover, the defendant 
entered eight counter claims against the plaintiff for approximately 
$5,500,000. The answer is sixty-six pages in length; the transcript of 
the testimony covers nearly ten thousand pages; there are 5,750 
exhibits; the defendant filed a brief of two thousand pages and requests
 for findings of fact that cover two hundred pages. Oral arguments were 
made April 28 to May 1 inclusive, 1946. The last brief was filed August 
25, 1946. The defendant's request for findings was filed and the case 
finally submitted to the court August 28, 1946.
The Pleadings.
The complaint is in six counts each based on a bill of lading for a 
shipment from each of the six points to Odair. The plaintiff alleges 
that land grant rates are applicable and in each count alleges the point
 of origin, the weight of the shipment, the land grant rate, the freight
 charges, the payment made and the balance due from the defendant. The 
facts alleged are summarized as follows:
Point of Origin    Weight     Land Grant        Charges      Payment     Balance
                             Rate Per Cwt.                               Claimed
Metaline Falls     689,604       26.83          $1850.21     $1172.33    $  677.88
Irvin              364,256       20.81            720.56       450.13       270.43
Seattle            256,640       21.78            558.96       436.29       122.67
Bellingham         484,680       25.19           1220.91       823.95       396.96
Concrete            89,780       24.23            217.54       152.62        64.92
Grotto             155,368       24.23            376.46       264.13       112.33
                                                                         _________
                             Total Balance Claimed Due.................. $1,645.19
The defendant alleges that the land grant rates are not applicable 
and that the charges for shipment of cement were subject to the 
provisions of a special rate contract, exhibit II, providing for a rate 
of 17¢ per cwt. from each of said points except Irvin which was 13¢ 
executed by and between the plaintiff and defendant November 19, 1934, 
under the Interstate Commerce Act, 49 U.S.C.A. § 22, and that the 
defendant has paid the plaintiff in full for all freight charges legally
 incurred.
The plaintiff admits the execution of the said contract but contends 
that it expired March 21, 1938, which was prior to the shipments of 
cement on which the charges are claimed in each instance and that the 
contract rates, therefore, do not apply.
The defendant pleads defenses as follows: (1) A general denial and 
allegations of payment in full; (2) that the bills of lading on which 
the complaint is based specified the rate for the transportation charges
 and, with the allegations of the complaint, constitute an admission of 
payment in full; (3) the special rate contract and full compliance 
therewith by the defendant; (4) fraud on the part of the plaintiff in 
procuring the execution of the rate contract by the defendant; (5) to 
(9) inclusive, estoppel or that the plaintiff should be denied the right
 to assert that the special rate contract covered only a portion of the 
cement used in the construction of the Grand Coulee dam and power plant 
on the ground that the plaintiff by misrepresentation and fraud induced 
the defendant to execute said contract and alter its position to its 
injury.
The defendant alleged that it was induced to execute the rate contract by the misrepresentation and fraud of the plaintiff 
*841 at the Denver Conference and in subsequent negotiations as follows:
1. 
Misrepresentations: a. The plaintiff represented to the 
defendant that there was no interchange gateway at Adrian, b. as there 
was no interchange gateway at Adrian, it would be necessary for the 
plaintiff to transport the cement from the West Coast points to Adrian 
via the long instead of the short route, c. if the government would 
build a branch railroad from Odair to the project site, the plaintiff 
would transport cement at sufficiently low rates to recompense the 
defendant, d. if the high dam were constructed, the plaintiff would 
build the branch line of railroad and make much lower rates than if only
 the low dam were constructed.
2. 
Concealments: a. an agreement between the plaintiff and 
the Great Northern Railway Company that neither would construct a branch
 line from Odair to the project site, b. the agreement between the 
plaintiff and the Great Northern Railway Company to open the Adrian 
gateway and transport cement from all West Coast points via the short 
route, c. the plaintiff's computations on land grant rates from the six 
Washington points which were correct and which averaged approximately 
2.73¢ less per cwt. than computations by the Bureau of Reclamation which
 were erroneous but on which the defendant relied, d. that the land 
grant rates from Trident, Montana, and Portland, Oregon, were lower than
 from the six Washington points except Irvin, e. that the plaintiff owns
 60,000 acres of land in the irrigable area.
The defendant alleged that in reliance on the misrepresentations and 
without the knowledge of the facts concealed by the plaintiff when it 
was under a duty to divulge them the defendant altered its position to 
its detriment as follows: a. its forbearance to build and operate a 
cement plant at the project site, b. its construction of the branch 
railroad thus eliminating all competition in transportation and giving 
the plaintiff a monopoly, c. abandonment of negotiations with other 
railroad systems and truck lines for the transportation of materials, d.
 agreement to rates that were not fair and reasonable to the defendant.
The defendant alleged counter claims as follows: (1) Sums paid by the
 defendant to the plaintiff in excess of fair and reasonable rates on 
shipments from the various Washington points to Odair, (2) sums paid by 
the defendant to the plaintiff in excess of fair and reasonable rates 
based on the cost of the transportation service to the plaintiff, (3) 
sums representing the difference in the cost of transporting the cement 
and materials over a long and circuitous route and the short direct 
route actually used, (4) sums in excess of 11¢ cwt. from Irvin and 15¢ 
cwt. from the other Washington points to Odair on shipments of cement, 
(5) cost of construction of the branch railroad from Odair to the 
project site in the sum of $646,400, (6) cost of maintaining and 
operating said railroad in the sum of $800,000, (7) overpayment to the 
plaintiff of freight charges on transportation of materials in the sum 
of $3,380,000, and (8) overpayment of freight charges on iron and steel 
supplies and shipment of numerous articles other than cement amounting 
to $417,661.54.
The defendant prays that the plaintiff's complaint be dismissed with 
costs; that the special rate contract be reformed, or, in the 
alternative, that it be rescinded and that the court fix the value of 
the plaintiff's transportation services on a quantum meruit basis; that 
the defendant have an accounting; that the defendant have judgment 
against the plaintiff for $5,500,000; for costs and for general relief.
The defendant moved for summary judgment on the pleadings, and the motion was overruled.
The validity and applicability of the special rate contract, exhibit 
II, hereafter called the rate contract, is the crux of this suit. Under 
the pleadings, it was deemed necessary to receive a mass of evidence not
 pertinent to the validity and applicability of the contract but bearing
 on 
*842 other issues raised by the 
pleadings. The purpose and background of the contract will be helpful in
 understanding the controversy.
The Project.
An empire within the state of Washington has remained almost wholly 
undeveloped for lack of moisture. The soil is exceedingly fertile, the 
climate ideal for the production of foods, yet only crops indigenous to 
semi-arid lands have been produced and the country now is sparsely 
populated and the lands are of little value. Men of vision for decades 
have sought a remedy for this situation. They have dreamed of a verdant 
countryside, comfortable homes, a larger population, beautiful cities 
and additional wealth. Strangely enough the necessary moisture has been 
at hand. The mighty Columbia River and its tributaries gather the waters
 of rains and melting snows from a vast area of plains and mountains and
 carry it in tremendous volume within easy reach of the thirsty soil.
However, a dam of mammoth proportions was necessary to capture and 
utilize the water of this surging river, and only some power or 
authority in command of almost unlimited financial resources and the 
finest engineering skill could produce it. The state had not undertaken 
it, and private capital perhaps wisely had not. Only the government of 
the United States safely could launch such an undertaking.
In addition to the value of such dam for irrigation purposes it could
 be made to produce a greater volume of electric current than any 
structure in the world, sufficient indeed, to supply many states of the 
northwestern area.
The proposal to construct such dam and irrigation system for many 
years was known as the Columbia Basin Project, and it had the active 
interest of Senators, Congressmen, civic organizations, influential 
citizens, three railroad systems including the plaintiff, and the state 
of Washington. Investigations had been made by the War Department and 
the United States Bureau of Reclamation and reports submitted to the 
effect that a dam of the Columbia River at the Grand Coulee was possible
 and practicable.
Plans, specifications and estimates were prepared. The dam from the 
base of the foundation to the top as designed would be higher than the 
Washington Monument. It would be 4,300 feet long, 500 feet thick at the 
base and would require 11,000,000 cubic yards of concrete. It would rest
 in a solid granite canyon and stop a river 800 feet wide and 50 feet 
deep which flows through the state of Washington for 750 miles and falls
 on its way some 1300 feet. It would raise the water level of the river 
370 feet and would produce a lake extending to the Canadian Border, a 
distance of approximately 125 miles. It would impound sufficient water 
to irrigate 1,200,000 acres of land and generate 2,700,000 horse power 
of electric current. It would be the key structure in a comprehensive 
plan for the development of the natural resources of the Columbia Basin 
and would become known as the "Eighth Wonder of the World."
The Grand Coulee location was selected because, from an engineering 
standpoint, the natural conditions at that place made the construction 
and operation of the dam most feasible and practicable, and because the 
Grand Coulee would create a reservoir of more than five million acre 
feet of useable capacity adjacent to the area to be served. An ancient 
bed of the Columbia River, appropriately called the Grand Coulee, was 
near the location for the dam. This coulee was 52 miles long, two to 
five miles wide and from 600 to 800 feet deep. It could be dammed at 
each end and a reservoir formed providing for gravity flow into the 
irrigation system. It was planned to use sufficient electric current 
generated at the dam to pump 16,000 cubic feet of water per second a 
vertical distance of 280 feet into the Grand Coulee Reservoir from which
 the flow for irrigation could be regulated.
It was estimated that the entire project would cost approximately $400,000,000. It required a dam at a cost of $208,000,000, 
*843
 an irrigation system at the cost of $200,000,000, and, in addition, a 
high elevation reservoir and extensive power and pumping machinery and 
equipment. The electric power switch yard at the plant cost $8,000,000. 
No action had been taken to finance such project prior to June 16, 1933.
 On that date the National Industrial Recovery Act, 48 Stat. 195, became
 a law and an appropriation of $4,000,000,000, to be used by the 
government to relieve unemployment, was made. The prospect of a large 
number of people being employed by the government naturally directed 
minds in the state of Washington to the Columbia Basin Project. This law
 opened the way, not only for the employment of 5,000 to 6,000 people, 
but also for the government to launch a long desired public enterprise, 
and so the sum of $63,000,000 was allotted for the construction of the 
Grand Coulee dam. This sum was estimated to be a small proportion of the
 cost of the complete project. It was recognized that the sum allotted 
would finance the construction of a plant that would utilize not more 
than 30% of the potential power of the river and that it would not 
provide for any irrigation. For various reasons it was believed 
necessary to keep the initial investment within the limits of the 
allotment made. Influences in other sections of the country and private 
power interests particularly were opposed to the project.
Plans were prepared for a dam that could be built within the sum 
allotted. This plan would raise the water level 150 feet, produce 
700,000 horse power of electric current but would not provide 
irrigation. It was in connection with this structure that specifications
 570 were prepared. Thus plans were developed for two dams, one of large
 proportions and the other much smaller in comparison. The greater 
structure became known as the "high" dam and the lesser the "low" dam. 
In the trial of this case much has been said about the high dam and the 
low dam. In the rate contract executed by the plaintiff and the 
defendant, the term "Grand Coulee dam and power plant" was used to 
designate the dam. The plaintiff contends that the term was used in the 
contract to describe the low dam while the defendant contends that it 
referred to the entire structure as completed. If the former, the 
contract was for the transportation of 1,600,000,000 pounds of cement; 
if for the latter, it was for 4,360,000,000 pounds. In other words the 
plaintiff claims that it contracted to carry the lesser quantity while 
the defendant claims that it contracted for the larger quantity. The 
difference is approximately two million dollars.
All interested persons wanted the high dam and no one wanted the low 
dam. The government engineers strongly advocated the construction of the
 high dam. However, it was decided to build the low dam and thus cut the
 garment according to the cloth. Whether the high dam would be 
constructed apparently depended at the time on whether the necessary 
funds would be forthcoming in the future.
The plaintiff had a very material interest in the construction of the
 high dam. It required three times as much material for the high dam as 
for the low dam. The difference in revenue was substantial. Moreover, 
the plaintiff owned about 60,000 acres of land in the irrigable area 
acquired largely through Congressional land grant. Of much greater 
importance was the fact that the plaintiff serves nearly 50% of the 
irrigable area and its development would produce revenues estimated at 
from $13,000,000 to $18,000,000 annually. The revenues to the plaintiff 
from transporting materials for the dam were of minor importance in 
comparison to the future benefits, if a dam providing irrigation were 
constructed.
Transportation.
Transportation of materials at the outset was recognized as a serious
 problem. The project site was thirty miles from Odair on the 
plaintiff's railroad, about the same distance from Mansfield on the 
Great Northern, and sixty-five miles from Neppel on the Milwaukee. 
Transportation other than by rail seemed impracticable. After extensive 
investigations and study, the government engineers obviously reached the
 conclusion that a branch railroad from Odair to the site of the project
 would be 
*844 the most practicable 
solution of the problem. The terrain from Odair to the site presented 
less engineering difficulties than from Mansfield or any other point.
The map of the state of Washington will be helpful. The Grand Coulee 
dam is slightly north of west and about 94 miles from the city of 
Spokane. The area is
*845 served by the lines of three 
railroad systems; the plaintiff, the Great Northern, and the Milwaukee. 
Bellingham, Concrete, Grotto, and Seattle are locations of the so-called
 West Coast mills. Two routes from the West Coast mills readily are 
discernible, the long route via the plaintiff's lines through Yakima, 
Pasco, Connell and West Warden, and the short route via the Great 
Northern through Grotto to Adrian thence via the Northern Pacific to 
Odair. These points are an average distance from Odair of 235 miles via 
the short route and 440 miles via the long route. Irvin near Spokane is 
130 miles and Metaline Falls in the northeast corner of the state is 249
 miles from Odair. From Metaline Falls shipments were made by the 
Milwaukee to Spokane or Rathdrum thence via the Northern Pacific to 
Odair. From Irvin shipments were made via the Northern Pacific Railway 
Company to Odair. The plaintiff's line makes contact with the Great 
Northern at Adrian which is 21.2 miles from Odair. The latter is about 
30 miles from the dam. The following table shows the difference in these
 routes:
Point of Origin     Rail Miles to Odair            Per Cent of Circuity
                    Long Route    Short Route
Bellingham              475           269                  77
Concrete                469           273                  72
Grotto                  448           158                 184
Seattle                 367           240                  53
Metaline Falls          315           246                  28
Irvin                   199           130                  53
The difference in these routes is important because the defendant 
contends that the agents of the plaintiff represented to the engineers 
of the government that the short route could not be used because there 
was not an interchange gateway at Adrian where the lines of the 
plaintiff contacted those of the Great Northern and that it was 
necessary to transport the cement from the West Coast mills via its 
lines an average distance of four hundred forty miles, that is, over the
 long route and that the rate necessarily had to be based on the cost of
 the service for that distance. The defendant contends that these 
representations were false at the time they were made by the plaintiff; 
and that, in any event a secret agreement was made by the plaintiff with
 the Great Northern Railway October 1, 1934, to open the Adrian gateway,
 which was nine and one-half months before the rate contract was signed 
by the Secretary and that it was the duty of the plaintiff to inform the
 defendant of such contract. With the exception of approximately sixteen
 thousand barrels used for bridge pier construction at the beginning of 
operations, all shipments of cement from the West Coast mills were made 
via the short route.
The plaintiff made application to the Interstate Commerce Commission 
November 3, 1933, for a certificate of public convenience and necessity 
authorizing the construction and operation of a line from Odair to the 
project site. The certificate was granted February 13, 1934, but in 
March of 1934 the plaintiff declined to construct such line. About this 
time a representative of the plaintiff importuned the commissioner of 
the Bureau of Reclamation at Washington to recommend to the engineers of
 the Bureau at Denver that the government construct such line, on the 
theory that the plaintiff would reduce freight rates on materials for 
the dam sufficiently to recompense the government for its cost. This 
situation led to the Denver Conference.
Denver Conference
Representatives of the plaintiff and defendant from March 28 to April
 4, 1934, met at Denver, Colorado, to consider the transportation 
problems particularly the construction of a branch railroad from Odair 
to the project site and freight rates for the transportation of 
materials required 
*846 for the project. 
This meeting has become known as the Denver Conference. It was attended 
by H. E. Stevens, Vice President, R. W. Clark, General Traffic Manager, 
now Vice President in Charge of Traffic, F. A. Cleveland, General 
Freight Agent, J. L. Burnham, Western Traffic Manager, and J. W. Haw, 
Director Agricultural Development Department, as representatives of the 
plaintiff. The government was represented by R. F. Walter, Chief 
Engineer, S. O. Harper, Assistant Chief Engineer, and Frank A. Banks, 
Construction Engineer, and a traffic clerk, Bureau of Reclamation. The 
rate contract which is of vital importance in this suit was the 
outgrowth of the Denver Conference.
The representatives of the plaintiff in the Denver Conference had 
devoted their active lives to the railroad business and not only were 
rate experts but also were entirely familiar with all phases of 
railroading. The objectives of the conference were railroad building and
 rate making, subjects with which they were well qualified to deal. In 
this conference they knew their own ground thoroughly and they knew 
precisely the situation of the government. They knew that it had 
$63,000,000 to spend on the Grand Coulee dam and power plant with a 
possibility of a much larger sum in the future, and that it desired to 
proceed as expeditiously as possible; that the project if completed 
would require the transportation of 6,000,000,000 pounds of material to a
 point then thirty miles from a railroad. They knew the necessity of an 
extension of a branch railroad either from the lines of the plaintiff, 
the Milwaukee or the Great Northern. They knew that a railroad from 
Odair to the project site would give the plaintiff a position of primacy
 that would enable it to dominate traffic and to make advantageous 
agreements with connecting lines for a division of revenues. They wanted
 the railroad and yet they had no intention of building it if they could
 induce the government to do so. Of course, they were fully aware of the
 fact that the plaintiff was under no legal duty to the defendant to 
construct such road. Therefore, the plaintiff had two principal 
objectives at the conference: (a) To induce the government to build a 
railroad from its station Odair to the project site and (b) to obtain a 
contract to transport the material for the project at the most 
satisfactory rates obtainable.
The representatives of the defendant in the Denver Conference were 
civil engineers of unquestioned skill, but they were not experienced in 
railroading or in rate making, the subjects of the conference, 
consequently, they were at a disadvantage. They desired immediate action
 to relieve unemployment and to commence the construction of a public 
enterprise of huge proportions. Because of the nature of the work, they 
were forced to show their hand. They were in no position to delay or to 
drive a bargain.
One difficulty of transcendent importance confronted both sides at 
the Denver Conference which was whether funds would be forthcoming to 
construct the high dam. At that time a sufficient sum had not been 
appropriated or allotted for that purpose. Every officer of the United 
States from the President down, who had anything to do with the project,
 favored it. In the conference the representatives of the plaintiff 
stated that if it could be assured that the high dam would be 
constructed, the plaintiff would build the branch railroad and agree to 
lower rates than if merely the low dam were constructed. The 
representatives of the United States, of course, could not give such 
assurance. Only Congress could do that.
The Denver Conference was opened with H. E. Stevens, Vice President, 
representing the plaintiff. The object of his presence was to inform the
 representatives of the government that the plaintiff would not build 
the branch road and if possible to induce them to use government funds 
for that purpose. He was not there to negotiate rates or to consider 
rates except to present the argument that, if the plaintiff were not 
required to construct the road, rates could be reduced on materials for 
the dam so as to recompense the government for the cost of the road. As a
 matter of fact, the plaintiff and the Great Northern had agreed that 
neither would construct such road. When Stevens and the government 
engineers had reached a tentative agreement for the construction of the 
road by the 
*847 government, Stevens 
terminated his negotiations. The result of his conference is outlined in
 his letter to the chief engineer for the Bureau dated March 28, 1934. 
The question of the construction of the branch road had been decided. 
The first objective of the conference had been attained by the 
plaintiff. In his letter he stated that responsible traffic officers of 
the company would confer with the representatives of the government and 
undertake to determine maximum rates that would be equitable and take 
into consideration all factors of the transportation problems. Clark, 
Burnham, and Cleveland, traffic officers, promptly appeared and 
negotiations for rates were opened.
At this conference each party was armed with an array of data 
pertaining to the subject under consideration. The negotiators had 
before them the plans, specifications and estimates of the low dam and 
the high dam, the maps showing the short and long routes from the cement
 mills to the site of the project and the tariff rates from possible 
points of origin to Odair. The plaintiff had calculated the cost of the 
service over the different routes and the possible revenue from low dam 
and from high dam quantities. The representatives of both the plaintiff 
and the defendant had calculated the land grant rates. The calculations 
of the plaintiff were correct, but those of the defendant were incorrect
 and were substantially higher than the actual land grant rates. 
Therefore, the plaintiff knew the land grant rates and the defendant did
 not but believed they were higher than they actually were. The 
calculations of the plaintiff were not revealed but those of the 
defendant were placed before the conference. The representatives of the 
plaintiff not only knew the land grant rates, but they also knew that 
the representatives of the defendant did not know them, and they knew 
that the representatives of the defendant believed the land grant rates 
were substantially higher than they actually were. The commercial rates 
and the land grant rates as calculated by the plaintiff and the 
defendant follow:
Point of Origin    Commercial      Calculations of Land
   to Odair           Rate             Grant Rates
                                   Plaintiff    Defendant
Bellingham            30.5¢           22.012¢       22.77
Concrete              30.5¢           21.836¢       22.79
Grotto                30.5¢           21.836¢       22.79
Seattle               30.5¢           18.058¢       20.87
Metaline Falls        27¢             24.2¢         25.93
Irvin                 20.5¢           18.6¢         19.27
The question of whether the low dam or the high dam would be 
constructed was considered because of its bearing on the quantity of 
materials to be transported. The route was important because of its 
bearing on the cost of the service which presumably was the basis for 
fixing the rates. The question of the interchange gateway at Adrian was 
involved because it was determinative of the route from the West Coast 
mills to Odair. This gateway at the time was closed but could be opened 
by agreement between the plaintiff and the Great Northern Railway 
Company. That an agreement for the interchange of shipments under a 
Section 22 contract with the United States could be effected must have 
been certain to the representatives of the plaintiff in the conference.
A tentative agreement was reached April 4, 1934. Negotiations were 
continued and the written contract placed in its final form some eight 
months later. It was outlined in the Clark letter of April 4, 1934, to 
the Chief Engineer. The contract was dated November 19, 1934. It was 
signed by the plaintiff March 4, 1935, and by the Secretary of the 
Interior July 17, 1935, fifteen and one-half months after the Denver 
Conference.
[1]
*848 A number of well settled principles of the law of contracts will be helpful:
The meaning of a contract should be ascertained from the language of 
the written instrument itself and where the provisions are plain and 
unambiguous the contract is conclusive. Miller v. Robertson, 
266 U.S. 243, 45 S. Ct. 73, 69 L. Ed. 265; De Witt v. Berry, 
134 U.S. 306,
 loc. cit. 312, 10 S. Ct. 536, 33 L. Ed. 896; Fogle & Co. v. United 
States, 4 Cir., 135 F.2d 117; International Co. of St. Louis v. Sloan, 
10 Cir., 114 F.2d 326; Pitcairn v. American Refrigerator Transit Co., 8 
Cir., 101 
*849 F.2d 929; Wm. Lindeke Land Co. v. Kalman, 190 Minn. 601, 252 N.W. 650, 93 A. L.R. 1393.
In the construction of contracts, language should be given if 
possible its usual and ordinary meaning and the object is to find out 
from the words used what the parties intended. Florida Central Railroad 
v. Schutte, 
103 U.S. 118, 26 L. Ed. 327; Ætna Insurance Co. v. Boon, 
95 U.S. 117,
 24 L. Ed. 395; United States v. Montgomery Ward & Co., 7 Cir., 150 
F.2d 369; Shell Oil Co. v. Manley Oil Corporation, 7 Cir., 124 F.2d 714.
A court will not resort to rules of construction where the intent of the parties 
*850
 is expressed in clear and unambiguous language. New York Life Insurance
 Co. v. Jackson, 7 Cir., 98 F.2d 950; Columbia Gas Construction Co. v. 
Holbrook, 81 F.2d 417; MacDonald v. Commissioner of Internal Revenue, 6 
Cir., 76 F. 513, 17 C.J.S., Contracts, § 294. p. 683.
A contract is ambiguous when it is reasonably and fairly susceptible 
to two different constructions. Order of United Commercial Travelers v. 
Sevier, 8 Cir., 121 F.2d 650; Blevins v. Reidling, 289 Ky. 335, 158 
S.W.2d 646.
A contract is not ambiguous where the court can determine its meaning
 without any other guide than a knowledge of the simple facts on which 
the language used depends for its meaning. National Pigments & 
Chemical Company v. C. K. Williams Company, 8 Cir., 94 F.2d 792.
In view of these principals the language of the rate contract claims attention. The 
*851
 agreement of the parties to this action should be determined from the 
contents of this document unless it is indefinite, uncertain or 
ambiguous. An analysis of the language pertaining to the issues in this 
case should be made.
The contract up to paragraph 12, except formal recitals, is devoted 
to the construction of the railroad from Odair to the project site. It 
was agreed that the defendant would furnish the right of way and 
construct, maintain, and operate the railroad; that the plaintiff would 
furnish to the defendant its preliminary surveys, plans, specifications 
and estimates for the construction of the railroad, and also furnish 
sufficient second-hand rails, angle bars, switches, and tie plates for 
sharp curves which were to be returned to the plaintiff; and that the 
contractor engaged to construct the dam would be required by the 
defendant to operate the railroad.
Section 13 of the contract placed the operation and maintenance of 
the branch railroad under the direct supervision and control of the 
United States and recited the fact that on July 16, 1934, the United 
States had made a contract with the Silas Mason Company and associates 
wherein it was "provided in Paragraph 51 of specifications No. 570, made
 a part of the contract," that the contractor would operate and maintain
 the railroad after its completion.
We are primarily concerned with Section 12 containing the rate fixing
 provisions of the contract. The points of origin and destination are 
designated. The contract covered cement shipped from the six designated 
Washington points only. It did not cover cement shipped from other 
places. The shipments had to be on "government bills of lading." The 
rates specified are designated as "maximum." The rates applied to cement
 for use in the construction of the "Grand Coulee dam and power plant." 
The paramount question for solution is what is meant in the contract by 
the "Grand Coulee dam and power plant." Does it mean the high dam or the
 low dam; or, in other words, does this provision of the contract cover 
the transportation of the cement for the dam as authorized by 
specifications No. 570 plus Change Order No. 1, or for the entire 
structure as completed? If there is anything in the contract that is 
indefinite, uncertain or in need of elucidation, it is the meaning of 
the language used to describe the dam. The meaning of perfectly correct 
language may be dependent on the circumstances under which it is used. A
 word may have no fixed legal significance as "premises" in O'Connor v. 
Great Lakes Pipe Line Co., 8 Cir., 63 F.2d 523. Unlike that word "Grand 
Coulee dam and power plant" has a very definite meaning; and yet, in 
view of the diverse contentions, an examination of the adoption of that 
description will be made.
It is contended by the government that "Grand Coulee dam and power 
plant" under the circumstances meant about what the United States 
desired to make it. In Paragraph 24
[2] of the specifications 
the government reserved the right to change the location, plans, 
alignment, dimensions or design of the dam; and in Paragraph 25
[3] it 
*852
 reserved the right, by order for a change, to discontinue the work 
under the contract and specifications on thirty days' notice and to 
proceed with the construction of a different dam with the same or 
another contractor. The plaintiff was fully aware of these provisions.
The contract of the government and the Mason Company dated July 16, 
1934, expressly made Specifications 570 a part thereof. The 
specifications gave the location and description of the dam, the date 
for beginning and completion of the work and comprehensive data 
describing in detail the project.
The only language in the contract about which there can be any 
controversy is the meaning of "Grand Coulee Dam and power plant." There 
are two letters on which the plaintiff strongly relies to sustain its 
position that the contract covers material for the low dam only. The 
letter of H. E. Stevens,
[4] Vice President of the plaintiff in charge of traffic, dated March 28, 1934, and 
*853 the letter of R. W. Clark,
[5]
 General Traffic Manager, who has succeeded Stevens, dated April 4, 
1934, both directed to R. F. Walter, Chief Engineer, Bureau of 
Reclamation.
In the Stevens letter reference is made to the "low dam project" and 
the "high dam project" and in the Clark letter reference is made to the 
"low dam unit at Grand Coulee." Obviously the authors of these letters 
at the time they were written had in mind the low dam and made reference
 to it by appropriate descriptions. These letters were written at the 
time of the Denver Conference when funds were available for 
*854
 construction of the low dam only, the dam under consideration, and the 
descriptions used in referring to the project were entirely appropriate.
 These letters were written more than one year and four months before 
the contract finally was executed. It had been drafted and redrafted 
many times. Numerous letters pertaining to it had been written and many 
conferences held. These letters were used as a basis for drafting the 
contract, but for some reason these terms were not acceptable to the 
government. The description "Grand Coulee dam and power plant" was used 
instead. It is reasonable to conclude that this was done in the Bureau 
of Reclamation so that any change could be made in the dam, as provided 
in the construction contract, without disturbing the provisions of the 
rate contract.
About the time of and shortly after the Denver Conference a number of
 important steps in rapid succession were taken in 1934 that showed 
conclusively that a dam would be constructed without delay. On bids 
opened March 19, 1934, the government purchased 16,000 barrels of 
cement, shipments of which were commenced May 10, 1934, via plaintiff's 
lines. Plans and specifications 570 for the construction of the low dam 
were completed April 16, 1934, and invitation for bids to build the 
railroad from Odair to the project site was issued April 20. An 
invitation to build the dam in accordance with specifications 570 was 
issued April 21, 1934. Bids for the construction of the railroad were 
opened May 17, and the contract therefor was executed July 17, and it 
was substantially completed by December 8. Bids for the construction of 
the dam were opened June 18, and the contract therefor was executed July
 16. A labor force was assembled; housing facilities provided; a bridge 
across the Columbia River was constructed; highways were improved; and 
necessary materials and machinery assembled. The President and the 
Secretary of the Interior inspected the project site August 3 and 
publicly announced that the high dam would be constructed. By the time 
the contract was signed in July, 1935, the plan to construct a low dam 
had been abandoned and it was definitely settled that the high dam would
 be constructed, so the description of the dam in the contract was 
changed accordingly.
The question here is what was in the mind of the parties at the time 
the contract was executed and not at the time of the Denver Conference 
or when the letters were written. As the situation developed, the 
officers of the Bureau obviously desired a contract covering such dam as
 might be constructed and the officers of the plaintiff just as 
obviously concluded to accept the change in description. As time 
advanced and it became certain that the high dam would be constructed, 
the intention of these participants advanced with the progress of 
developments to the thought that this contract should cover the 
materials for such dam as the government might construct. The evolution 
of the minds of the parties is indicated by a comparison of the language
 of the Stevens and Clark letters with that of the contract. When the 
contract was executed by the plaintiff in March and the defendant in 
July, 1935, with full knowledge that the high dam then was being 
constructed, manifestly both parties accepted Grand Coulee dam and power
 plant to mean the high dam. In Cowles Electric Smelting & Aluminum 
Co. v. Lowrey, 6 Cir., 79 F. 331, 344, the court said:
"It is a well-established doctrine that a party must be deemed to 
have assented to the contract in such a sense as he knew the other party
 intended it to signify, provided the language employed is capable of 
such a meaning. And we have no doubt that for the purpose of construing 
this contract we must suppose that the parties intended to deal with 
existing things, and in the form and character in which they existed."
If nothing other than the Stevens and Clark letters appeared in the 
record, the consent to the change possibly might be regarded as an 
oversight on the part of the officials of the plaintiff, but it was not 
an oversight; to the contrary it was a subject of discussion by them and
 for the consideration of the plaintiff's legal department. Plaintiff's 
General Manager on June 11, 1934, in a letter to the plaintiff's Vice 
President said: "Paragraph 12 provides for maximum freight rates and for
 reduction by agreement, and the contract is indefinite 
*855
 in term, the inference being from Paragraph 15 (Paragraph 20 of the 
contract as executed) that it shall be in effect for at least ten years,
 though apparently it might remain in effect indefinitely, even were the
 railroad removed at the end of ten years. * * * It is possible to 
conceive that increased costs due to six-hour day and increased wages 
might make these rates unremunerative before the end of five years, and 
yet we apparently would be required to handle the business at them for 
as long as the government desired we should." The Assistant General 
Counsel of the plaintiff in a letter dated July 6, 1934, in commenting 
on the contract said: "I do not find in the agreement anywhere a 
sufficient definition of or reference to `high dam' to make the 
provision intelligent. I suggest that you work this out more in detail *
 * *." The suggestions of the General Manager and Assistant General 
Counsel were not followed or adopted by the plaintiff, but the executive
 officers in charge of the matter left the contract unchanged as to term
 and as to description of the project. The present contention that the 
contract terminated when the work of the Mason Company was completed 
does not comport with the position of the General Manager and the 
Assistant General Counsel when the contract was being written. They 
executed the contract for the transportation of materials "for use in 
the construction of the Grand Coulee dam and power plant" with full 
knowledge of the scope of that description. Perhaps the contract, 
including the provision for the construction of the railroad by the 
United States, and the construction of the high dam involved too much 
for the plaintiff to risk tampering further with it, but signed it 
knowing that it might be construed to cover the high dam. This contract 
was executed for the defendant by the Secretary of the Interior who did 
not attend any of the conferences leading to the execution of it or see 
any of the letters or documents pertaining to it. Nothing was submitted 
to the Secretary except the contract. Consequently, these letters cannot
 be accepted as conclusive proof that the contract at the time it was 
signed was limited to the low dam, especially when the contract might 
have been made explicit by the insertion of the one word "low" or the 
words of either of the letters provided the intention still existed to 
limit the contract to the low dam. These letters are not a part of the 
contract. They are a minor portion of the negotiations leading to the 
execution of the contract. When a contract is reduced to writing all 
matters of negotiation and discussion on the subject antecedent to and 
dehors the writing are excluded as being merged in the instrument. 
DeWitt v. Berry, supra; Van Ness v. Mayor, Aldermen and Board of Common 
Council of City of Washington, 
29 U.S. 232, 7 L. Ed. 842; Nash v. Towne, 
72 U.S. 689,
 18 L. Ed. 527; Cohen v. New England Mutual Life Insurance Co., 7 Cir., 
140 F.2d 1. In Volume I Restatement of the Law of Contracts, Section 
237, the rule is stated as follows:
"* * * the integration of an agreement makes inoperative to add to or
 to vary the agreement all contemporaneous oral agreements relating to 
the same subject-matter; and also, unless the integration is void, or 
voidable and avoided, all prior oral or written agreements relating 
thereto. If either void or voidable and avoided, the integration leaves 
the operation of prior agreements unaffected."
Attention is directed to Section 20 of the contract. This section 
relates to the return of the rail and fastenings to the plaintiff on the
 completion of the Grand Coulee dam and power plant with a proviso that 
if on completion thereof it appears that the United States will, within a
 few years thereafter proceed to increase the heighth of the dam, the 
plaintiff will not require the return of the rail and fastenings till 
the high dam is completed and with an additional proviso that if there 
is no decision as to the construction of the high dam within ten years, 
the rail and fastenings will be returned to the plaintiff. The argument 
is made that these provisos show the intention of the government to 
build a low dam and that it might later decide to increase the heighth 
of the dam and that, therefore, the rate contract applied to the 
material for the low dam only. The conclusion does not follow the 
premise. The section relates to the return, and the time of the return, 
of the equipment furnished by the plaintiff for 
*856
 the railroad. This section obviously was drafted at a time when it 
appeared that it was advisable to begin the construction of a low dam 
only and that an increase in the heighth of such dam was merely a 
possibility. Certainly this provision would not limit the right of the 
government to exercise its privileges under the contract and 
specifications for the construction of a dam with such changes or 
alterations as it deemed appropriate, nor does it limit the scope of the
 designation "Grand Coulee dam and power plant" as used in the rate 
making provisions of the rate contract nor does it relieve the plaintiff
 of its obligations under that contract to transport the material for 
such dam as the government saw fit to build at Grand Coulee. At this 
point it should be observed that there was no delay at any time in the 
work of building the dam to completion after it had been commenced. 
There was no intermission between the completion of the first unit and 
the beginning of the second. The work was accelerated from the beginning
 to the end, with the exception of installation of generators. Funds 
were allotted from time to time and the entire structure was practically
 completed within a period of six years. Section 20 contemplated the 
construction of the high dam and the section as a whole is as consistent
 with the conclusion that the rates provided in Section 12 are as 
applicable to the high dam as to the low dam.
The plaintiff contends that the rate contract terminated with the 
completion of the work under the Mason contract which was on March 21, 
1938, the date on which the work of that company was accepted. Before 
construction on the dam was commenced, it obviously was decided to 
construct the high dam in successive units in the event funds were not 
made available for the entire project as required. Therefore, Change 
Order No. 1 to Specifications 570 was prepared May 24, signed June 5, 
1935, by the Secretary the purpose of which was to thicken the base and 
otherwise change the dimensions of the structure so as to make it more 
appropriate for the base of a high dam. Strange as it may seem this 
change order was signed forty-two days before the rate contract for the 
transportation of cement was signed by the Secretary. The low dam was 
abandoned before construction was commenced. The first cement was poured
 November 28, 1935.
On November 3, 1937, when the foundation for the dam was nearing 
completion, the defendant issued invitations for bids to finish the 
Grand Coulee dam and power plant. Because of the magnitude of the 
proposal, the contractors, Mason and associates, instead of filing a 
competitive bid, joined with others and submitted a bid under the name 
of the Consolidated Builders, Inc. The bids were opened December 10, 
1937, and the contract was awarded to Consolidated Builders, Inc., 
February 7, 1938. The Mason contract according to its terms was to 
terminate April 3, 1939, but the defendant by a change order terminated 
its contract March 21, 1938, thus advancing the termination date by more
 than one year. The Consolidated Builders, Inc., immediately took charge
 of operations, the unused materials, the machinery and equipment, the 
labor force and proceeded, without interruption, under preexisting 
methods to complete the structure. Shipments of cement to the defendant 
were continued in accordance with the rate contract, shipments were made
 on the conventional bills of lading specifying the rates provided by 
the contract, and bills for freight charges were submitted and paid in 
the accustomed manner.
The rate contract imposed on the plaintiff the duty to transport from
 six designated Washington points to Odair cement for the Grand Coulee 
dam and power plant; and it was quite immaterial whether the contractor 
who was engaged by the government to do the work of construction was the
 Mason Company, the Consolidated Builders, Inc., or some other. There is
 nothing in the contract that precluded the government from engaging 
many contractors for the construction of the dam; neither is there any 
limitation on the right of the government to make changes in its plans 
and specifications for the dam. It could build a low dam or a high dam 
without disturbing its contractual relations with the plaintiff, 
provided the cement transported was for the Grand Coulee dam and power 
plant. There is nothing in the contract that limits its duration to the 
period the Mason Company was engaged in performing 
*857
 its part of the work. Reference is made to the contract with the Mason 
Company in Section 13, but this section is merely a recital of a fact 
and imposes no obligation on either party to the rate contract. This 
provision was inserted at the request of the plaintiff undoubtedly as an
 assurance that the government and its contractor had the responsibility
 of constructing and operating the railroad and that the plaintiff did 
not.
When the change order was made June 28, 1935, abandoning the plan for
 the low dam and substituting therefor the foundation for the high dam, 
the plaintiff made inquiry whether the change would affect prospective 
revenues from the project; but it did not concern itself about a change 
in rates, the terms of the contract or a change in the description of 
the dam. Although the plaintiff, during the fifteen months the contract 
was in the course of preparation, proposed numerous and important 
changes, no objection was raised to the designation Grand Coulee dam and
 power plant.
As the foundation of the dam was nearing completion, information 
became known that the Bureau of Reclamation contemplated asking a 
reduction in rates on cement below the maximum specified in the rate 
contract. The observation was made by the Bureau that the rate contract 
expressly provided for a revision of rates by agreement of the parties, 
that the rates designated were "maximum", that the government had 
constructed the railroad and that all question of the construction of 
the high dam long since had been settled. During a period of 
approximately three years many thousands of carloads of materials had 
been transported to the site and the government had proceeded with the 
construction of the dam. During that period little or nothing, so far as
 appears, had been said by the parties relative to a change in rates. No
 contention had been made that the rate contract did not cover materials
 for the high dam.
Washington Conference.
About April 1, 1938, the plaintiff commenced negotiations with the 
Procurement Division of the Treasury Department at Washington, D. C., 
for an increase in rates on materials for the high dam. A conference was
 held April 11, 1938, by the president and vice president of the 
plaintiff with H. E. Collins, Assistant Director, and W. E. Hayghe, 
Chief of the Traffic Section of the Division. In connection with this 
conference a letter
[6] to the Secretary of the Interior, not dated but mailed and received in the Department of the Interior April 15, 
*858
 1938, was prepared by Hayghe. This letter was signed by the assistant 
director who testified that he signed it without reading it or knowing 
what was in it; and, if he had known, he would not have signed it. This 
letter informed the Secretary that the rate contract applied only to the
 materials used in the construction of the low dam, that it had expired 
and that under authority of the President dated April 12, 1935, 
negotiations had been opened with the plaintiff for establishing a new 
schedule of rates.
The information contained in the director's letter was relayed to the Chief Engineer at Denver in a letter
[7]
 by L. B. Williams, Assistant Commissioner of the Bureau of Reclamation,
 on May 5, 1938, in which he stated that the Procurement Division had 
informed the Bureau that the rate contract had expired, that new rates 
were being negotiated with the plaintiff and that they would be higher 
than in the former contract.
On receipt of the Williams letter R. F. Walter, Chief Engineer, directed a letter
[8] to the Commissioner of the Bureau of Reclamation May 17, 1938, in which he strongly contended that the rate contract 
*859
 had not expired but was in full force and effect and covered the 
transportation of materials for the completion of the Grand Coulee dam 
and power plant; or in other words, that it covered not only the 
materials used by the Mason Company for the foundation but also the 
materials used or to be used by the Consolidated Builders, Inc. in the 
completion of the Grand Coulee dam and power plant.
It is significant that this conference was held without notice to the
 Secretary of the Interior or the Bureau of Reclamation and that no one 
representing the Interior Department was present, especially when it is 
remembered that the Interior Department had negotiated the rate contract
 with the plaintiff, was constructing the dam and had supervision of the
 entire project, and when it is remembered 
*860
 that all the transactions of the plaintiff had been with the Bureau at 
Denver and none with the Procurement Division at Washington. The 
plaintiff had made no request of the Bureau for an increase in rates. 
Application was made to a different bureau of a different department in a
 distant city and to officers who had no information pertaining to the 
rate contract or the project. The plaintiff undertakes to justify its 
action in proceeding before the Procurement Division because of the 
executive action of April 12, 1935, to place traffic matters in the 
Treasury Department. The matter came to the hand of one W. E. Hayghe, a 
subordinate in the Procurement Division. The Stevens and Clark letters 
were presented to him and a statement made from the plaintiff's point of
 view whereupon Hayghe, without ascertaining the position or point of 
view of the Interior Department, obviously jumped to the conclusion that
 the contract had expired. The plaintiff relies on these letters to show
 the position taken by the government at the time they were written. 
Public officers are merely officers of the public, whose powers and 
authority are defined and limited by law, and any act without the scope 
of the authority so defined does not bind the principal, and all persons
 dealing with such agents are charged with knowledge of the extent of 
their authority. Whiteside et al. v. United States, 
93 U.S. 247, 23 L. Ed. 882; United States v. Barlow, 
132 U.S. 271, 10 S. Ct. 77, 
*861
 33 L. Ed. 346; Continental Casualty Co. v. United States, 5 Cir., 113 
F.2d 284; 46 C.J. 1033. The conclusions stated in the letters were made 
without a hearing, without investigation, without knowledge of the 
subject, and without authority to change or terminate the rate contract.
 Collins or Hayghe or the Procurement Division had no power to alter or 
terminate a contract that had been executed on behalf of the defendant 
by the Secretary of the Interior or state a position on it that would in
 any way bind the United States.
The Washington Conference ended in a stalemate. The defendant 
contends that the plaintiff had two objectives in view: (1) To escape 
the rate contract on materials for the high dam so it could have the 
benefit of the 10% rate increase, applicable to the area, which had been
 allowed shortly prior to the Washington Conference, and (2) that, if 
the provisions of the rate contract could not be avoided, the plaintiff 
at least might be able to forestall the government in an effort to 
secure lower rates. In the second objective the plaintiff was 
successful.
On the failure of the Washington Conference the plaintiff in its 
freight bills demanded tariff rates less applicable land grant 
deductions. The government refused to pay such rates on the ground that 
the rate contract still was in effect. The plaintiff continued to 
perform the service and the defendant continued to pay the contract 
rates. In any event a new contract was 
*862 not made and the parties proceeded under the terms and conditions of the old.
Kenney Telegram.
The telegram
[9] of W. P. Kenney, President of the Great 
Northern to a Vice President in charge of traffic dated March 17, 1938, 
is significant in connection with the duration of the rate contract. It 
was sent at the time of the rate agitation just prior to the Washington 
Conference. The Mr. Donnelly mentioned in the telegram was President of 
the plaintiff. It shows that the Presidents of the roads had an 
"understanding" which the President of the Great Northern "thought 
covered the cement movement to Grand Coulee on everything that moves." 
He further stated that he "did not know there was any necessity for 
making a new agreement." This had reference to the effort to negotiate a
 new rate contract at the Washington Conference. Furthermore, he stated 
that he and Mr. Donnelly agreed "on the rate and divisions in connection
 with building of road over to Grand Coulee Dam and I don't think there 
will be any misunderstanding regarding it." These poignant statements 
show that when the companies made their agreement October 1, 1934, the 
President of the Great Northern at least believed that the rate contract
 applied to "everything that moves," and that "a new agreement was not 
necessary." Clearly there was no idea in the mind of the President of 
the Great Northern that the rate contract covered cement for the low dam
 only.
Equities.
The law does not protect against conditions, harsh though they may 
be, which a party to a contract voluntarily has imposed on himself. 
Trancontinental & Western Air, Inc., v. Parker, 8 Cir., 144 F.2d 
735; Tahir Erk v. Glenn L. Martin Co., 4 Cir., 143 F.2d 232; Shell Oil 
Co., Inc., v. Manley Oil Corporation, 7 Cir., 124 F.2d 714; Summers v. 
Travelers Insurance Co., 8 Cir., 109 F.2d 845. It is not the function of
 the court to make a new contract for the parties. Columbia Gas Const. 
Co. v. Holbrook, 6 Cir., 81 F.2d 417; Order of United Commercial 
Travelers v. Shane, 8 Cir., 64 F.2d 55; O'Connor v. Great Lakes Pipe 
Line Co., 8 Cir., 63 F.2d 523. But, if there is a question of 
interpretation, the court should endeavor to adopt the construction 
which is most equitable to the parties and will not give to one of them 
an unreasonable advantage over the other; in other words, where a 
contract is capable of an interpretation in accordance with justice and 
fair dealing the court will adopt such construction. Phillips Petroleum 
Co. v. Gable, 10 Cir., 128 F.2d 943; Bayne v. United States, 8 Cir., 195
 F. 236; Champlin v. Commissioner, 10 Cir., 71 F.2d 23; Foye Lumber Co. 
v. Pennsylvania Railroad Co., 8 Cir., 10 F.2d 437; Leschen & Sons 
Rope Co. v. Mayflower Gold Mining & Reduction Co., 10 Cir., 173 F. 
855, 35 L.R.A.,N.S., 1; City of Orlando v. Murphy, 5 Cir., 84 F.2d 531.
To adopt the construction of the contract advocated by the plaintiff,
 namely, that the termination of the Mason Contract by the government on
 March 21, 1938, and the acceptance of the work done under it, 
automatically terminated the special rate contract would give the 
plaintiff a position of decided advantage and place the defendant in a 
predicament. At that time only the foundation of the Grand Coulee dam 
and power plant had been constructed. The government had five thousand 
employees engaged on the work, a vast quantity of materials on hand and 
on order, had expended a million dollars on the construction and 
operation of a branch railroad which had to be junked on completion of 
the dam, was holding aside the waters of a tremendous river and was 
ready to proceed 
*863 with the work to 
completion when it was notified through the Procurement Division at 
Washington that the special rate contract had expired and that a new 
contract providing for higher rates was necessary, or that tariff rates 
less land grant deductions would be exacted.
The reasons why the plaintiff is one of the greatest benefactors of 
this public improvement and the advantages of the rate contract to the 
plaintiff have been stated but certain other facts should have attention
 in connection with the interpretation of the rate contract. On the 
negotiation of this contract, the plaintiff entered into division 
agreements with its connecting lines, the Great Northern and the 
Milwaukee. When these divisions are considered with the service rendered
 by the respective carriers, the bonanza held by the plaintiff may be 
more clearly understood.
The agreement with the Great Northern provided for a division of 55% 
of the revenue to the plaintiff and 45% to the Great Northern on the 
shipment of cement from the West Coast mills to Odair. The Great 
Northern transported this cement from the West Coast mills over the 
mountains to Adrian, an average distance of 235 miles. The plaintiff 
transported the cement from Adrian to Odair a distance of 21.2 miles 
where it was delivered to the government contractor. The plaintiff 
performed 9% of the service and the Great Northern 91%. Of the 17¢ per 
cwt., the plaintiff received 9.35¢ and the Great Northern 7.65¢. The 
plaintiff received 1.70¢ per cwt. more for performing 9% of the service 
than the Great Northern received for performing 91% of it. The shipments
 from the West Coast mills totaled 36,742 carloads on which the 
government paid freight of $5,461,580.50, producing to the Great 
Northern average ton mile earnings of $.00653 and to the plaintiff 
$.08905 or 12.7 times as much to the latter as to the former.
An agreement with the Milwaukee provided for two-thirds of the 
revenue to the plaintiff and one-third to the Milwaukee on shipments 
from Metaline Falls. The Milwaukee transported the cement from Metaline 
Falls to Spokane or Rathdrum where it was received by the plaintiff and 
transported to Odair. The Milwaukee performed 51% of the service and of 
the 17¢ per cwt. received 5.667¢ to Spokane or 4.658¢ to Rathdrum while 
the plaintiff received 11.333¢ if the exchange was at Spokane or 12.342¢
 if at Rathdrum. Freight on shipments from Metaline Falls amounted to 
$932,689.
Approximately thirteen thousand carloads of materials other than 
cement were shipped from various parts of the country at tariff or land 
grant rates on which the government paid freight of $2,263,869.71. On 
all these shipments the government favored the lines of the plaintiff 
where possible. Shipments of cement from Trident and Portland were made 
in 1939 because the western mills were unable to supply the volume 
required by the government. The special rate contract did not apply to 
these points of origin and land grant rates were paid. Freight on 423 
carloads from Trident amounted to $78,031.72 and on 1,335 carloads from 
Portland the freight was $404,323.21.
The plaintiff's revenue per car on cement from Adrian to Odair in the
 years 1935 to 1939 ranged from $88.43 to $96.47 and on this service the
 plaintiff calculated its "out-of-pocket" cost at $3.75 per carload. An 
important factor, of course, was the movement of the freight by the 
plaintiff a distance of only 21.2 miles.
The valuation placed on the patronage resulting from the construction
 of the dam by the Great Northern and the Milwaukee is revealed by the 
willingness of the one to accept 45% of the pay for 91% of the service 
and of the other to accept one-third of the pay for 51% of the service. 
The connecting lines furnished a proportionate part of the freight cars 
used for the transportation of materials. The government paid all of the
 cost of installing and 65% of the cost of operating the interchange 
facilities at Odair. Obviously there were strong reasons why the 
executives of the plaintiff did not insist on the description of the dam
 in the rate contract being changed to cover the low dam in explicit 
terms.
It may be said that the terms of the division contracts between the 
carriers was their own business and of no concern to the defendant; yet,
 these facts elucidate a situation involving equities of the respective 
parties herein that the court 
*864 may 
take into consideration in its effort to arrive at a fair interpretation
 of the contract. On the question of construction, the plaintiff is not 
entitled to claim special favors, especially as the evidence is as 
cogent that the contract covered the cement for the high dam as it is 
that it applied to the low dam only. The rule in 17 C.J.S., Contracts, §
 318, p. 735 may be applied.
"Where a word or words, or the contract as a whole, is susceptible of
 two meanings, one of which will uphold the contract or render it valid 
or enforceable, while the other will destroy it or render it invalid or 
ineffective, the former will be adopted. So, a contract should be 
construed in favor of mutuality, certainty, and legality; and a 
construction imputing good faith and absence of fraud, or rendering 
performance possible, will be preferred to a contrary construction."
Fraud.
It is asserted that the government was induced by the 
misrepresentation and fraud of the plaintiff to execute the rate 
contract. This argument certainly is inconsistent with plaintiff's 
contention that the contract is valid and applicable to the 
transportation of the cement from the Washington mills for use in 
construction of the entire dam. Furthermore, the issue is presented at a
 late hour. After what has been said, an analysis of the evidence 
bearing on the question of fraud is unnecessary and this phase of the 
controversy requires only brief attention.
It is well settled that to constitute actionable fraud the injured 
party must have had the right to rely on the representations or 
concealments alleged to have been made. A party may not rely on another 
to disclose superior information which the latter may possess, in the 
absence of confidential relations. Roosevelt v. Missouri State Life 
Insurance Co., 8 Cir., 78 F.2d 752; Upton v. Tribilcock, 
91 U.S. 45,
 23 L. Ed. 203; Horton et al. v. Reynolds et al., 8 Cir., 65 F.2d 430; 
Slaughter's Adm'r v. Gerson, 13 Wall. 379, 20 L. Ed. 627; 37 C.J.S., 
Fraud, § 30, p. 271.
In the Roosevelt case, supra [78 F.2d 762], Judge Sanborn in a concurring opinion said:
"This court, however, has long been of the view that in actions to 
recover damages for fraud, the misrepresentations must not only have 
been relied upon, but must have been of such a nature or made under such
 circumstances that the plaintiff had a right to rely upon them."
In Restatement of the Law of Torts, Section 546, the rule is stated as follows:
"The maker of a fraudulent misrepresentation in a business 
transaction is liable for pecuniary loss caused to its recipient by his 
reliance upon the truth of the matter misrepresented if his justifiable 
reliance upon the misrepresentation is a substantial factor in 
determining the course of conduct which results in his loss."
The Denver Conference was a bargaining negotiation. One witness 
designated it a "horse trading affair." Many offers and counteroffers 
were made. The participants were intelligent, experienced men of 
affairs, dealing at arm's length with each other. There was nothing in 
it indicating fiduciary relations. The evidence shows that each side had
 much data on the subjects under consideration. While the 
representatives of the government were not railroad experts and were "in
 a hurry to get started", they could have called for conference agents 
of the Great Northern, the Milwaukee, and the Union Pacific. They could 
have called to their aid the employees of the Interstate Commerce 
Commission, the Public Service Commission of Washington, and the experts
 of the General Accounting Office, "a court of last resort" on the 
calculation of land grant rates. They could have had full and complete 
information pertaining to the routes, the Adrian gateway, the cost of 
service, what would have been fair and reasonable rates and all other 
information and facts that would have been helpful. The relations of the
 parties were not such as to excuse investigation and justify reliance 
on information coming from parties representing adverse interests. 
Consequently, the United States is precluded from asserting fraud in 
this case for the simple reason that its representatives had no right 
under the circumstances to rely on what was said by the agents of the 
plaintiff in the 
*865 Denver Conference 
and in subsequent negotiations. Therefore, fraud is not a basis for a 
cause of action, a defense or a counterclaim by the defendant against 
the plaintiff in this case; neither was the rate contract vitiated by 
fraud.
It may be appropriate to add that the government became fully aware 
of the facts several years prior to the completion of the dam; and, if 
it considered that it had been defrauded or that the contract rates were
 unreasonable, it could have proceeded before the Interstate Commerce 
Commission in interstate matters and before the Public Service 
Commission of Washington in intrastate matters to secure a reduction. 
However, as this court holds the rate contract applicable to the 
transportation of all the cement from the six Washington points for the 
dam as constructed, it is unnecessary to determine the question of 
jurisdiction to fix rates. See Watab Paper Co. v. Northern Pacific 
Railway Co., 8 Cir., 154 F.2d 436; Thompson, Trustee et al. v. Baltimore
 & Ohio Railroad Co. et al., 8 Cir., 155 F.2d 767; Great Northern 
Railway Co. et al. v. Merchants Elevator Co., 
259 U.S. 285, 42 S. Ct. 477, 66 L. Ed. 943; Mitchell Coal & Coke Co. v. Pennsylvania Railroad Co., 
230 U.S. 247, 33 S. Ct. 916, 57 L.Ed 1472; Texas & Pacific Railway Co. v. Abilene Cotton Oil Co., 
204 U.S. 426,
 27 S. Ct. 350, 51 L.Ed 553, 9 Ann. Cas. 1075; Belcher v. Tacoma Eastern
 R. Co., 99 Wash. 34, 168 P. 782; Hewitt Logging Co. v. Northern Pacific
 Railway Co., 97 Wash. 597, 166 P. 1153, 3 A.L.R. 198; State v. Metaline
 Falls Light & Water Company, 80 Wash. 652, 141 P. 1142; Northern 
Pacific Railway Company v. Sauk River Lumber Co., 9 Cir., 82 F.2d 519.
For several years both parties carried on operations under the rate 
contract without complaint; in fact till one party wanted an increase in
 rates and the other wanted a reduction. For an additional period of 
five years both continued operations in accordance with the terms of the
 contract. Except the filing of this suit on November 4, 1939, no action
 was taken by either party.
Rescission.
The defendant claims the right to rescind the rate contract. 
Rescission is the termination or the unmaking of a contract. A voidable,
 executory contract may be rescinded on proper grounds. However, a 
contract which is fully executed cannot be rescinded. Merchants' Bank v.
 Hanna, 8 Cir., 73 F.2d 818. One claiming that a contract was obtained 
by fraud, promptly must elect to rescind or be denied that relief on the
 ground of ratification. If one proceeds to execute the contract, or 
receive the benefit under it, knowing that he is being defrauded, or if 
he in any way recognizes it as a subsisting and binding agreement, he 
will be deemed to have affirmed the contract and waived his right to 
rescind.
A right to rescind must be exercised within a reasonable time after 
discovery of the facts from which the right arises. Brite v. W. J. Howey
 Company, 5 Cir., 81 F.2d 840; Nelson v. Chicago Mill & Lumber 
Corporation, 8 Cir., 76 F.2d 17, 100 A.L.R. 87.
Generally an affirmative act on the part of one desiring to rescind 
is necessary. Andrew v. American Sav. Bank & Trust Co., 219 Iowa 
921, 258 N.W. 911; Mannon v. Pesula, 
59 Cal. App. 2d 597, 139 P.2d 336; Huth v. Picotte, Mo.App. 154 S.W.2d 382.
In this case the defendant at no time gave notice of intention to 
rescind but proceeded for a long period of time under the contract. 
Indeed, the Chief Engineer of the Bureau of Reclamation in charge of the
 Denver office on May 17, 1938, three years after the contract had been 
signed in a letter to the Commissioner of the Bureau strongly contended 
that the contract was still in force and effect. Throughout the 
operations to the end of 1942 the contract was treated as a subsisting 
and binding obligation. The contract has been substantially performed in
 all respects. This case was presented by the defendant on the theory 
that the contract covers the transportation of materials for the dam as 
completed; consequently, there is no ground for rescission.
Reformation.
The defendant seeks a reformation of the contract. Reformation is an equitable remedy by which a written instrument 
*866
 is made or construed to express the real intention of the parties when 
some error or mistake has been committed. Equity has power to reform and
 correct a valid written instrument to make it conform to the agreement 
actually made. A proceeding to reform a contract presupposes that the 
instrument does not express the true intent of the parties. It 
contemplates a continuance of the contractual relation. Its purpose is 
not to make a new contract but to give effect to the original intent of 
the parties. Cramp & Sons Ship & Engine Bldg. Co. v. United 
States, 
239 U.S. 221, 36 S. Ct. 70, 60 L. Ed. 238; Bartelme et al. v. Merced Irrigation District, 9 Cir., 31 F.2d 10.
Where reformation is sought because of the mistake of one party only,
 it is essential that fraud be found in the other and that the fraud was
 perpetrated to induce the making of the contract, and, although a 
ground for rescission and cancellation, it is not a ground for 
reformation. Where because of ignorance or mistake on one side and fraud
 on the other the contract does not accurately state the agreement made,
 its reformation may be authorized. Columbian National Life Insurance 
Co. v. Black, 10 Cir., 35 F.2d 571, 71 A.L.R. 128; Westinghouse Electric
 & Mfg. Co. v. Tri-City Radio Electric Supply Co., 8 Cir., 23 F.2d 
628; Southern Surety Co. v. United States Cast Iron Pipe & Foundry 
Co., 8 Cir., 13 F.2d 833.
In this case there is no ground for reformation because the written 
contract fully and accurately expressed the agreement made by the 
parties and, in fact, there is no contention to the contrary. Moreover, 
the contract has been substantially terminated by performance.
Bill of Lading Provision.
The government bills of lading for shipment of the cement from the 
Washington mills to Odair had stamped thereon "Special rate of 17¢ cwt. 
per contract Ilr-804 with the Northern Pacific Railway dated August 7, 
1935." The government contends that acceptance of shipments on such 
bills created a contract for carriage at the 17¢ rate even if the 
special rate contract had expired. The acceptance of the shipments on 
bills bearing that notation was not an agreement to the rate, or 
acquiescence in the rate or a waiver of objections to it. The 
performance of such service by a common carrier cannot be construed as a
 waiver of its rights or consent to an obligation that otherwise does 
not exist under the law or a contract. Chicago & Northwestern 
Railway Company v. United States, 
104 U.S. 680,
 26 L.Ed 891. The government was advised of the plaintiff's position and
 was not mislead or deceived in any way by the action of the plaintiff 
in accepting the shipments on the bills of lading bearing the notation. 
At the time the shipments involved herein were made, the United States 
was engaged, at the height, in the construction of the dam and refusal 
to transport the shipments immediately would have interfered with the 
progress of the work and have resulted in heavy loss to all parties 
concerned. The plaintiff should have rendered the service, as it did, 
and leave to an appropriate tribunal the responsibility of determining 
rate and contractual disputes.
Freight bills were submitted on usual forms for tariff rates less 
land grant deductions. These bills were allowed by the defendant at 
contract rates and the plaintiff received the money. A bill for the full
 sum claimed was presented to the appropriate officer and a portion was 
deducted. The plaintiff did not indicate satisfaction with the sum 
allowed. No action or omission of the plaintiff induced the making of 
the deduction. Acceptance of the sum allowed is not a bar to a claim for
 the balance in the courts of proper jurisdiction. St. Louis, B. & 
N. Ry. v. United States, 
268 U.S. 169, 45 S. Ct. 472, 69 L. Ed. 472.
Conclusions.
The Grand Coulee dam and power plant is a magnificent monument to the
 ability, energy, and ingenuity of R. F. Walter, Chief Engineer, S. O. 
Harper, Assistant Chief Engineer, and Frank A. Banks, Construction 
Engineer. This structure was substantially completed in a period of six 
years, and the hydroelectric plant was placed in operation in time to 
supply current to extensive war industries. The 
*867
 Columbia Basin Project is nearing completion and will be a lasting 
benefit to the people of the Northwest area. The economic success of the
 enterprise is assured.
The rate contract has been performed. When it was executed, the 
parties knew that the high dam was under construction. It was valid and 
applicable to the movement of cement from the six Washington mills to 
Odair for the dam as constructed. Furthermore, there was no provision in
 the contract limiting it to the low dam or its duration.
The plaintiff and its connecting carriers transported the cement, 
delivered it to the government's contractor and were paid as the 
contract provided, and, this includes the shipments covered by the bills
 of lading on which this suit is based; in other words, the plaintiff 
has performed its part of the contract, has received contract rates for 
its service on shipments covered by the contract and on all other 
shipments it has been paid tariff rates less applicable land grant 
deductions.
As the validity and applicability of the contract to the dam as 
constructed are sustained, the plaintiff is not entitled to recover on 
its alleged cause of action, and the defendant is not entitled to 
recover on any of its alleged counterclaims. Thus the court leaves the 
parties where it found them, which, in all fairness and justice, is 
precisely what each is entitled to receive in this suit.
Findings of Fact, Conclusions of Law, and an Order for Judgment will be entered accordingly.
NOTES
[1]  The Contract: Exhibit II
      "United States         I1r-804
      "Department of the Interior
        "Bureau of Reclamation
  "Grand Coulee Dam and Power Plant
  "Columbia Basin Project, Washington
"Contract between United States of America and Northern Pacific 
Railway Company for construction of standard-gauge construction railroad
 from Odair, Washington, to Grand Coulee dam site.
"1. This contract, made this 19th day of November 1934, in pursuance 
of the act of Congress of June 16, 1933 (48 Stat. 196), known as the 
National Industrial Recovery Act, between The United States of America 
(herein styled the United States), acting in this behalf by Harold L. 
Ickes, Secretary of the Interior (herein styled the Secretary), and the 
Northern Pacific Railway Company, a corporation of the State of 
Wisconsin (herein styled the Company), having its principal place of 
business at St. Paul, Minnesota. Witnesseth:
"2. Whereas, the United States is engaged under the National 
Industrial Recovery Act in constructing the Grand Coulee dam and power 
plant of the Columbia Basin project, in the State of Washington, and, as
 a part of such work, proposes to construct a standard-gauge 
construction railroad from Odair, Washington, a siding on the Northern 
Pacific Railroad, about two miles northeast of Coulee City, Washington, 
to the Grand Coulee Dam site, on the Columbia River, about thirty miles 
northeast of Coulee City, Washington, consisting of yard tracks at Odair
 for the purpose of interchanging and storing cars, a single-track 
railroad from Odair to the head of Grand Coulee, a siding at the head of
 Grand Coulee, a single-track railroad from the head of Grand Coulee to 
the Grand Coulee Dam site, and a siding near the dam site; and
"3. Whereas, it is contemplated that the contractor for construction 
of the Grand Coulee dam and power plant (herein styled the Contractor) 
will operate and maintain the construction railroad after its 
completion; and
"4. Whereas, the Company has heretofore made surveys for such a 
railroad, and is willing to turn over to the United States all data 
covering such surveys and suggestions for the construction of such 
railroad without charges; and
"5. Whereas, the Company is willing to furnish to the United States, 
free of charge, f. o. b. cars at Odair, Washington, sufficient rail and 
fastenings to complete the construction of such railroad, including 
yard, tracks and sidings, from a connection with the Washington Central 
Branch of the Company at Odair, Washington, to the Grand Coulee Dam 
site; and
"6. Whereas, the Company is willing to establish maximum net cash 
freight rates on certain materials, supplies and equipment moving on 
Government bills-of-lading and used in the construction of the Grand 
Coulee dam and power plant,
"7. Now, therefore, in consideration of the premises and of the 
covenants and conditions herein contained, it is agreed between the 
parties as follows:
"8. The United States will construct a standard-gauge railroad to 
extend from Odair, Washington, on the Washington Central Branch of the 
Company, about two miles northeast of Coulee City, Washington, to the 
Grand Coulee Dam site, on the Columbia River, about thirty miles 
northeast of Coulee City, Washington, as shown on the location map 
hereto attached, marked Exhibit A, made a part hereof, such railroad to 
consist of yard tracks for the purpose of interchanging and storing cars
 at Odair, a single-track railroad from Odair to the head of Grand 
Coulee, a siding at the head of Grand Coulee, a single-track railroad 
from the head of Grand Coulee to the Grand Coulee Dam site, and a siding
 near the dam site.
"9. The United States will furnish the right-of-way for the railroad 
and will perform the necessary work of construction, and will furnish, 
at its own expense, all supplies and materials going into the railroad, 
except second-hand rail, angle bars, switch material and tie plates for 
use on sharp curves.
"10. The Company will turn over to the United States, without charge,
 complete data covering the preliminary surveys for the railroad as 
heretofore made by the Company, and will stake out on the ground the 
definite center-line location of the railroad, and will also make 
available to the United States the Company's plans, specifications, and 
estimates for construction of the railroad.
"11. The Company will also furnish to the United States, without 
charge, f. o. b. cars at Odair, Washington, sufficient suitable 
secondhand 90-lb. rail, angle bars, frogs, switches, and tie plates for 
sharp curves, to complete the construction of the railroad as specified 
in Article 8. It is understood that the demurrage agreement hereinafter 
provided for will apply to the cars of track material after acceptance 
by the United States.
"12. The following maximum rates, in cents per hundredweight, are 
hereby established by the Company on cement moving over existing rail 
routes in cars loaded to maximum capacity from certain points, as herein
 listed, in the State of Washington to Odair, Washington, on Government 
bills-of-lading, for use in construction of the Grand Coulee dam and 
power plant:
       Irvin              13¢
       Metaline Falls     17¢
       Bellingham         17¢
       Concrete           17¢
       Seattle            17¢
       Grotto             17¢
On the balance of the items of materials, supplies and equipment to 
be used in the construction of the Grand Coulee dam and power plant and 
moving on Government bills-of-lading, the established commercial freight
 rates over existing routes, less land-grant deduction, shall apply, 
with the following exceptions:
"(1) From Seattle and Tacoma, Washington, the established commercial 
freight rates applicable from Portland, Oregon, over existing routes, 
less land-grant deduction, on iron and steel articles and machinery 
shall apply;
"(2) The following maximum rates shall apply on lumber and cribbing
    From Sand Point, Idaho,        18¢
    From Coeur d'Alene, Idaho,     14¢
    From Spokane, Washington,   12½¢
The rates hereinabove shall not be increased or decreased during the 
term of this contract unless in the opinion of the United States and the
 Company such rates become inequitable because of changed conditions. If
 the necessity arises for revising said rates or for the fixing of rates
 on additional items or from additional points, adjustments will be made
 in the established rates or such new rates will be made as may be 
agreed to by the authorized representatives of the Company and the 
United States.
"13. Operation and maintenance of the railroad will be under the 
direct supervision and control of the United States. The United States 
having heretofore, under date of July 16, 1934, entered into a contract
"(Symbol No.12r-4359) with Silas Mason Company, Inc., a New York 
corporation, the Walsh Construction Company, an Iowa corporation, and 
the Atkinson-Kier Company, a partnership consisting of Guy F. Atkinson, 
George H. Atkinson, William E. Kier and Elmer L. Kier of San Francisco, 
California (for convenience now styled collectively the Contractor), 
wherein it is provided in paragraph 51 of Specifications No. 570, made a
 part of the said contract, that the Contractor will operate and 
maintain the railroad after its completion, the Contractor will be 
required to provide reasonable service thereunder for handling the 
business of the United States and others during the period of the said 
contract.
"14. The United States agrees to interchange loaded and empty cars 
with the Company at Odair and to handle same in the manner usual between
 common-carrier railroads. The Company will deliver cars upon such 
tracks in said yard as may be mutually agreed upon between the United 
States and the superintendent of the Company. The United States will 
deliver cars to the Company upon tracks designated for that purpose in 
said yard. The United States agrees not to operate engines or cars 
nearer to the tracks of the Company than a point to be marked on the 
ground by the Company designating where engines or cars of the United 
States shall stop.
"15. All cars and equipment placed by the Company on the designated 
tracks in said interchange yard shall be deemed to be in the possession 
of the United States and to continue in the possession of the United 
States from the time so placed upon said designated tracks by the 
Company until the Company shall move said cars from said yard onto its 
own tracks. The United States shall pay the Company demurrage accruing 
on all cars and equipment owned by the Company and on cars and equipment
 owned by others for which the Company is responsible while such cars 
and equipment are in the possession of the United States, but such 
demurrage charge shall not be made after the United States has notified 
the Company that such cars and equipment are available for the use of 
the Company at Odair and may be removed from such interchange yard. All 
settlements for such demurrage shall be made in accordance with the 
terms and provisions of the American Railway Association Freight Tariff 
4-N, I.C.C.No. 2639, B. T. Jones, Agent, naming national car demurrage 
rules and charges, supplements thereto and reissues thereof including 
the average basis for settling for detention to cars.
"16. The United States shall be responsible for loss of or damage to 
cars and equipment of the Company and cars and equipment owned by others
 for which the Company is responsible, while such cars and equipment are
 in the possession of the United States, ordinary wear and tear 
excepted.
"17. In the event the United States shall operate the railroad, then 
it is agreed that, except in cases were liability results solely from 
negligence of the Company, the Company does not and shall not assume any
 liability for injury to or death of any person or persons or loss of or
 damage to any property, when such injury, death, loss or damage is 
caused by, results from, or arises during and in consequence of the 
operations by the United States.
"18. The Contractor for operation of the railroad, as referred to in 
Article 13, shall furnish the Company with an indemnity agreement 
protecting the Company against any and all claims arising or growing out
 of alleged defects in cars and equipment owned by the Company and cars 
and equipment owned by others for which the Company is responsible.
"19. The Company shall provide such employees and facilities as may 
be necessary for maintaining and operating interchange facilities at 
Odair, and the costs thereof, other than maintenance of trackage, will 
be equally divided between the Company and the United States. The 
Company shall render quarterly to the United States itemized bills 
covering such costs, plus fifteen per cent to cover superintendence and 
expenses not possible of exact ascertainment.
"20. The United States shall return to the Company, without cost, f. 
o. b. cars at Odair, Washington, all rail and fastenings furnished to 
the United States by the Company in as good condition as when furnished 
by the Company, ordinary wear and tear excepted, promptly on completion 
of the Grand Coulee dam and power plant; 
provided that if, on 
completion of the dam and power plant, it appears probable that the 
United States will, within a few years thereafter, proceed with the work
 of increasing the height of said dam, the Company will not require 
return of the rail and fastenings until the said high dam has been 
completed; and 
provided further that, if no decision as to the 
construction of the proposed high dam is reached within a period of ten 
years from the date of this agreement, the United States will, on demand
 of the Company, pick up and return the rail and fastenings to the 
Company, free of charge, f. o. b. cars at Odair, Washington; and 
provided
 further that, at the option of the United States, the Company will pick
 up the rail and fastenings and the United States shall pay to the 
Company the actual cost of doing such work.
"21. No member of or delegate to Congress, or resident commissioner 
shall be admitted to any share or part of this contract or to any 
benefit that may arise therefrom, but this provision shall not be 
construed to extend to this contract if made with a corporation for its 
general benefit.
"22. The performance by the United States of any obligation 
undertaken hereunder involving the expenditure of money is dependent 
upon the availability of appropriated funds and/or allocated public 
works funds for the purpose, and in all cases where such funds are not 
available the United States is hereby released of all claims on account 
of such nonperformance due to such nonavailability.
"In Witness Whereof, the parties hereto have signed their names the day and year first above written.
"The United States of America,
    "By /s/ Harold L. Ickes,
            "Secretary of the Interior.
     "Northern Pacific Railway Company,
        "By /s/ Charles Donnelly, Pres.
"(Seal) Attest:
  "A. M. Gottschald, Asst. Secy."
[2]  Section 24:
"When additional information regarding foundation or other conditions
 becomes available as a result of the excavation work, further testing, 
or otherwise, it may be found desirable to change the location, 
alignment, dimensions, or design of the dam or power plant to meet such 
conditions. The Government reserves the right to make such reasonable 
changes as, in the opinion of the contracting officer, may be considered
 necessary or desirable, and the contractor shall be entitled to no 
extra compensation because of such changes, except that any increase in 
the amount of excavation, concrete, or other required work, for which 
items are provided in the schedule, will be paid for at the unit prices 
bid therefor in the schedule. The contractor's plant shall be laid out 
and his operations shall be so conducted as to accommodate any 
reasonable change in the location and design of the dam and power plant,
 or any part thereof, without additional cost to the Government."
[3]  Section 25:
"If at any time within the contract period, the construction of the 
Grand Coulee dam to the full height contemplated for the ultimate 
development of the project, is authorized, the Government shall have the
 right to terminate the contract under these specifications upon thirty 
(30) days' notice in writing to the contractor, and, in such event, the 
contractor shall turn over to the Government, free of encumbrance, all 
plant, tools, and equipment of the contractor, including camp and 
appurtenances, which are installed at the time of such termination or 
contracted for in writing, in use or to be used exclusively in the work 
under these specifications, and, at the option of the contractor, shall 
include consumable supplies of the contractor, on hand or in transit on 
the date of the notice of termination, including explosives, fuel, 
lubricants, and materials of construction not incorporated in the work, 
but shall not include commitments for the purchase of consumable 
supplies or construction materials extending beyond the date of the 
notice of termination."
[4]  Stevens Letter:
  "Denver, Colorado, March 28, 1934
"Mr. R. F. Walter, Chief Engineer,
  "Bureau of Reclamation,
  "Denver, Colorado
"Dear Sir:
"Confirming our verbal understanding this morning, the Northern 
Pacific Railway Company agrees to furnish f. o. b. Coulee City, 
sufficient rail and fastenings to complete the construction of a 
railway, including yard, tracks and sidings, from a connection with the 
Washington Central Branch near Coulee City to the head of the Grand 
Coulee Canon. We will also turn over to you the complete data covering 
our preliminary survey for this railway and agree to stake out on the 
ground definite location of center line, also furnish subject to your 
approval, specification for its construction. No charge to be made by 
the railway company for the use of the rails or for the survey data and 
engineering work.
"The Government agrees to include in its specifications and proposal 
blanks, covering the construction of the Grand Coulee Low Dam project, 
items to cover grading, ballasting, track laying and surfacing of the 
above described railway on a right-of-way to be furnished by the 
Government. It will also require the successful bidder to proceed with 
the construction of this railway with all possible dispatch promptly on 
the award of the general contract.
"The Government further agrees that it will return to the railway 
company without cost to it, f. o. b. cars Coulee City, all rail and 
fastenings loaned to it by the railway company promptly on completion of
 the Low Dam Project. Provided, however; that, if on completion of this 
project, it appears probable that the Government will, within a few 
years thereafter, proceed with the construction of the High Dam Project,
 the railway will not require the return of the rails and fastenings 
until the High Dam Project has been completed. If no definite decision 
on construction of the High Dam is reached within a period of ten (10) 
years from date, the Government will, on demand of the railway company, 
pick up and return the rail and fastenings to the railway free of 
charge, f. o. b. Coulee City; at the option of the Government the 
railway will pick up the rail and fastenings, the Government to pay the 
railway the actual cost of doing the work.
"The Government agrees to require its general contractor to maintain 
the railway and to provide reasonable service thereover for handling the
 business of the Government and others throughout the contract period. 
Revenues for handling other than Government business over the railway to
 accrue to the Government but to be entirely independent of rates fixed 
by the railway company for delivery of materials at the interchange 
point of connection with its Washington Central branch.
"It is my understanding that the above conditions are acceptable to 
you provided we can agree on maximum rates for major items of material 
shipped on Government bills of lading. A responsible traffic officer of 
our company will confer with you not later than April 3rd, 1934 and 
undertake to determine these maximums on a basis that will be equitable 
and take into consideration all factors of your transportation problem.
"I am enclosing herewith estimated quantities of principal items 
entering into the construction of the proposed railway as determined 
from our preliminary survey.
"Yours truly,
         "H. E. Stevens
         "Vice President
"HES/JC     Northern Pacific Railway"
[5]  Clark Letter:
"Northern Pacific Railway Company
"Traffic Department
"R. W. Clark,             St. Paul, Minn.
  "General Traffic Manager
                   "At Denver, Colorado
                         "April 4, 1934
"Dear Sir:
"Under the plan that the Government will finance the construction of a
 railroad from Odair to the Grand Coulee dam site on the basis outlined 
in Mr. Stevens' letter to you of March 28, 1934, the Northern Pacific 
Railway Company will quote to point of connection with this proposed 
line net cash rates, in cents per hundred weight, as shown herein, as 
maximum rates on material moved on Government bills of lading and used 
in the construction of the so-called low dam unit at Grand Coulee.
"The tonnages on material used in this computation are those shown on
 statement you furnished, headed `Estimated Freight Costs on Material 
for Low Dam Grand Coulee  Columbia Basin.' The total tonnage of 
materials as shown on that statement is 1,800,000,000 pounds, or 900,000
 tons; and of this total, 1,600,000,000 pounds, or 800,000 tons, is 
cement.
"It is our understanding that it will be the policy of the 
Government, so far as possible, to use in the construction of this unit 
materials originating in the State of Washington.
"You furnished us information that the six cement plants shown on your statement have a daily capacity in barrels as follows:
Irvin ............................. 1,800
Metaline Falls .................... 1,650
Bellingham ........................ 2,700
Concrete .......................... 3,500
Seattle ........................... 3,300
Grotto ............................ 1,650
                                   ______
        Total                      14,600
"You indicated that it would be your policy to divide the order on a 
prorate basis on the capacity of the plant, question of quality being 
satisfactory.
"The Railway Company proposes as maximum net cash rates on cement as follows:
Irvin ........................ 13¢
Metaline Falls ............... 17¢
Bellingham ................... 17¢
Concrete ..................... 17¢
Seattle ...................... 17¢
Grotto ....................... 17¢
"We will apply on the balance of the items listed in the first three 
classes of your statement the commercial rates less land grant 
deduction, with following exceptions:
"(1) We will quote from Seattle and Tacoma the net cash rate 
applicable from Portland on iron and steel articles and machinery; and
"(2) We will quote on lumber and cribbing as maximum rates;
   From Sand Point      18¢
    "   Coeur d'Alene   14¢
    "   Spokane         12½¢
"I understand from our discussions that, if the cement is bought from
 present existing plants, the rates quoted in this letter will insure 
movement of this cement via existing rail routes.
"I appreciate the opportunity you have given to discuss these 
matters, and we will be glad to work out with you from time to time such
 adjustments as may be necessary to meet any fair competition that may 
develop as the work proceeds.
"Very truly yours,
                 "SGD R. W. Clark
"Mr. R. F. Walter,
"Chief Engineer, Bureau of Reclamation
"Denver, Colorado
"I am agreeable to the above arrangement.
"SGD R. F. Walter
"Denver, Colo.             Chief Engineer"
[6]  Collins Letter:
"Treasury Department Procurement Division Washington
"In Reply Address
   Branch of Supply
   and refer to file No.
"The Honorable,
  "The Secretary of the Interior.
"My dear Mr. Secretary:
"Attention is invited to contract dated November 19, 1934, between 
the Department of Interior and the Northern Pacific Railroad Company for
 the construction of a standard-gauge railroad from Odair, Washington, 
to the Grand Coulee Dam Site.
"Among other things, the contract provides for the application of 
special rates to apply on cement, lumber and cribbing moving from 
various points of origin to Odair, Washington, the point of interchange 
between the Northern Pacific and the Government constructed railroad 
serving the dam site. These rates, however, are limited by certain 
provisions of the contract to apply only on materials used in the 
construction of the so-called low dam and power plant, and with the 
completion of that part of the work the special rates expired.
"The Bureau of Reclamation has recently entered into a new contract 
for the heightening of the dam which will result in the purchase of 
large quantities of materials, including approximately six million 
barrels of cement. At the present time the only rates available for 
application to Odair, Washington are the published commercial rates, 
less deductions account of land grant, which are substantially in excess
 of the special rates made effective on materials used in the first 
phase of the work.
"Under authority of Order of the President dated April 12, 1935, this
 office has opened negotiations with the Northern Pacific Railroad 
Company for the establishment of a new scale of special rates, but 
definite action is being withheld pending opening of bids to cover the 
requirements of the Bureau of Reclamation, it being understood that 
whatever special rates are finally approved will apply retroactively on 
any actual shipments which may move in the meantime.
"In addition to those paragraphs of the contract having to do with 
freight rates, it is probable that the extension or amendment of certain
 other provisions of the contract may be desirable on the part of the 
Department, there being no provision made in the instrument for a 
continuation of the terms with the exception of the matter contained in 
Paragraph 20. This office will communicate the result of its 
negotiations for new special rates in order that this action may be 
coordinated with action taken by the Department with respect to other 
factors.
"Very truly yours,
                    "H. E. Collins
                   "Assistant Director."
[7]  Williams Letter:
                          "May 5, 1938
"From: Commissioner
"To: Chief Engineer, Denver, Colorado
"Subject: Freight charges on cement, Columbia Basin Project, Grand Coulee Dam.
"1. Reference is made to your letter of April 25, on the subject 
above named, also to Construction Engineer's letter of April 19, 
together with letter dated April 15, from Mr. A. L. Wielde, Northern 
Pacific Railway.
"2. The Procurement Division advises that they will negotiate new 
rates with the Northern Pacific Railway Company to supersede those in 
contract No. I1r-804, which expired with the completion of the M. W. A. 
K. contract. An agreement has already been reached to await award of 
contracts for cement for the Consolidated job to see from what mills the
 cement will move and then agree as to the new rates, which will be 
retroactive. Mr. Hayghe advises that the new rates will be somewhat 
higher than those in the old contract.
"3. The rate question is affected by S. 3876 introduced in the Senate
 by Senator Wheeler, which has been approved by the Interstate Commerce 
Committee. This bill proposes to do away with all Government land grant 
rates. Mr. Hayghe states that no companion bill has been introduced in 
the House, and that he does not look for favorable action at this 
session of Congress.
"For the Commissioner
"/s/ L. B. Williams
                   "Assistant Commissioner
"CC: Const. Engr., Coulee Dam."
[8]  States "Department of the Interior "Bureau of Reclamation "Customhouse
"Denver. Colorado
"Office of the Chief Engineer
"May 17, 1938.
"From    Chief Engineer
"To    Commissioner
"Subject: Freight charges on cement  Grand Coulee Dam  Columbia Basin Project.
"1. Receipt is acknowledged of your letter of May 6, on the above 
subject, enclosing for consideration and report, copy of undated letter 
addressed to the Secretary by the Assistant Director of the Procurement 
Division, Treasury Department. Reference is also made to your letter of 
May 5, subject, `Freight charges on cement  Columbia Basin Project  
Grand Coulee Dam,' and related correspondence.
"2. In paragraph 2 of your letter of May 5, you state that `The 
Procurement Division advises that they will negotiate new rates with the
 Northern Pacific Railway Company to supersede those in contract No. 
I1r-804, 
which expired with the completion of the M. W. A. K. contract. * * * Mr. Hayghe advises that the 
new rates will be somewhat higher than those in the old contract.'
 (Underscoring ours.) In the second paragraph of the letter from the 
Procurement Division the statement is made that `These rates, however, 
are limited by certain provisions of the contract to apply only on 
materials used in the construction of the so-called low dam and power 
plant, and with the completion of that part of the work 
the special rates expired.'
"3. The views expressed in the above quotations do not comport with 
the understanding reached in this office at the time the contract of 
November 19, 1934, was negotiated with officials of the Northern Pacific
 Railway Company, nor with our present construction of its terms, and 
this office is particularly concerned about the underscored portions of 
the quotations.
"4. Regarding the conclusion which has apparently been reached by the
 Procurement Division and representatives of the railway company that 
the contract of November 19, 1934 expired upon completion of the M. W. 
A. K. contract, the following comment is submitted. The pertinent 
provisions of the contract relating to this point are contained in 
articles 12 and 20. Article 12 provides that:
"`The following maximum rates * * * are hereby established by the 
Company on cement * * * for use in construction of the Grand Coulee dam 
and power plant.'
Article 20 provides that,
"`The United States shall return to the Company * * * all rail and 
fastenings * * * promptly on completion of the Grand Coulee dam and 
power plant; provided that if, on completion of the dam and power plant,
 it appears probable that the United States will, within a few years 
thereafter, proceed with the work of increasing the height of said dam, 
the Company will not require return of the rail and fastenings until the
 said high dam has been completed; and provided further that, if no 
decision as to the construction of the proposed high dam is reached 
within a period of ten years from the date of this agreement, the United
 States will * * * pick up and return the rail and fastenings to the 
Company.'
In view of the fact that decision to proceed with the construction of
 the base of the high dam instead of the so-called low dam was reached 
soon after the contract with the railway company was entered into, thus 
changing to some extent the assumptions upon which the contract was 
based, and resulting in some ambiguity in the application of certain of 
the provisions, it seems appropriate, in determining the proper 
interpretation of the contract provisions, to take into consideration 
the circumstances under which it was written as determining the intent 
of the parties when the contract was negotiated, as evidenced by the 
understanding of those who participated in the negotiations.
"5. The expression `Grand Coulee dam and power plant' was intended to
 cover the completion of such structure as might be built at Grand 
Coulee prior to suspension of the work for an indefinite period. No 
mention is made in the contract of the so-called `low dam' and had it 
been intended to confine the application of the contract to the low dam,
 this would have been specifically stated. There was good reason to 
believe, even at that time, that the work would not stop prior to 
completion of the high dam and power plant, and the provision in article
 20 for termination of the contract upon the expiration of ten years was
 inserted only on the insistence of the Company's representatives. This 
office does not concede that the term `Grand Coulee dam and power plant'
 is restricted in meaning to the so-called `low dam,' but the work 
accomplished under the M. W. A. K. contract as well as the work now in 
progress under the Consolidated Builders, Inc. contract is all part of 
the construction of Grand Coulee Dam and Power Plant. Certainly no one 
can reasonably contend that the contract expires prior to the lapse of a
 period of ten years, as provided in article 20, provided the high dam 
has not been completed. In other words, the contract, in our opinion, 
expires, (a) upon completion of the high dam, or (b) ten years from the 
date of the agreement of November 19, 1934. It is not conceded that any 
part of the contract can be considered as expiring before the final date
 of termination, and the only manner in which the rate structure can be 
changed is by mutual agreement in accordance with the provisions of the 
last seven lines of article 12. Further justification for this view will
 be hereinafter brought out in the discussion of the proposed rate 
structure.
"6. The negotiations in Denver leading up to agreement on the terms 
of the contract were participated in, on the part of the railroad 
company by Mr. R. W. Clark, Vice President in charge of traffic, Mr. J. 
L. Burnham, Western Traffic Manager, and Mr. B. A. Cleveland, General 
Freight Agent. The representatives of the Bureau, citing the 
construction of the Boulder City branch of the Union Pacific as a 
precedent, contended that the Northern Pacific should be willing to 
build the Grand Coulee branch line at its own expense. The point was 
stressed that the tremendous volume of traffic resulting from the 
construction of the low dam then authorized, as well as the high dam 
which was certain to be built, would fully justify the construction of 
the railroad by the Company without expense to the Government. Mr. 
Clark, however, refused to concede that the high dam would ever be built
 and insisted that the Company could not afford to build the branch line
 for the low dam only, and he further refused to concede that the rate 
structure should be based on the anticipated traffic from the high dam.
"7. In negotiating the rate structure, the Bureau representatives 
held out for a rate on cement from coast points of 15¢ per hundred, on 
two grounds; 1st, that the tremendous volume of traffic which the 
railroad company would receive before the high dam was completed would 
fully justify this rate; second, that the rate structure should be based
 on the short haul of from 137 to 256 miles from West Coast cement mills
 to Adrian by the Great Northern, rather than on the long haul of about 
465 miles by the Northern Pacific via Pasco. We insisted that this 
cement would never be hauled by the circuitous Northern Pacific route, 
but Mr. Clark was equally insistent that it would be so routed and that 
the freight rate should be based on the long haul. The Bureau 
representatives finally yielded and agreed to tentatively accept the 17¢
 rate, although we were convinced that it was not equitable if the 
material should move via the Great Northern, and also if the work on the
 high dam should proceed without interruption. To protect the Government
 in the event that our assumptions were correct, we insisted on placing 
in the contract a provision for a downward adjustment of rates, which 
accounts for the following provision in article 12:
"`The rates hereinabove shall not be increased or decreased during 
the term of this contract unless in the opinion of the United States and
 the Company such rates become inequitable because of changed 
conditions. If the necessity arises for revising said rates or for the 
fixing of rates on additional items or from additional points, 
adjustments will be made in the established rates or such new rates will
 be made as may be agreed to by the authorized representatives of the 
Company and the United States.'
It should be mentioned that the word `decreased' was inserted at the 
request of the railroad officials, even though Mr. Clark positively 
stated that there would be no request for an increase by the railroad 
company.
"8. Under date of December 23, 1935, before cement shipments began to
 move, the Northern Pacific Railway Company addressed a letter to the 
Traffic Manager of the Interior Department advising that an 
understanding had been reached with the Great Northern whereby all 
cement originating at West Coast mills would be handled by the Great 
Northern to Adrian, thus confirming the contention which we had made 
that these shipments would never move by the circuitous Northern Pacific
 route. It is of interest to note in this connection that the Great 
Northern receives 45% of the 17¢ rate, or $.0765, and the Northern 
Pacific receives 55%, or $.0935. The length of haul over the Great 
Northern from West Coast mills to Adrian averages 215 miles, while the 
haul over the Northern Pacific from Adrian to Odair is 21.2 miles. The 
revenue received by the Great Northern averages $.0071 per ton-mile, 
while the Northern Pacific receives $.0882 per ton-mile.
"9. These figures show conclusively that there is no justification 
whatever for an increase in the rate of 17¢, as the revenue now received
 by the Northern Pacific for the haul of 21.2 miles from Adrian to Odair
 is out of all proportion to the cost of this service, as well as to the
 division of the revenue received by the Great Northern. When the 
further circumstances above mentioned are considered, namely, that the 
branch railroad from Odair to the dam was constructed at the expense of 
the Government, with the exception of the loan of rail and fastenings, 
and that the construction of the high dam with the tremendous amount of 
traffic resulting therefrom, will be prosecuted without delay, there is 
every justification for demanding that the present rate of 17¢ per 
hundred from coast mills be reduced, and that a corresponding adjustment
 be made in the rates from the two Eastern Washington mills.
"10. This office does not have a copy of the Executive order dated 
April 12, 1935 which is cited by the Procurement Division as authority 
for opening the negotiations with the Company, but it would appear that 
the contract of Nov. 19, 1934, having been executed on behalf of the 
United States by the Secretary of the Interior, cannot properly be 
terminated or amended except by the same official. However, if the 
Procurement Division is charged with the responsibility of handling 
these negotiations, it is recommended that strong representations be 
made to that office that:
"(a) There is no justification for concluding that the contract of Nov. 19, 1934, has expired; and
"(b) That no upward adjustment of freight rates for cement or other 
materials for Grand Coulee Dam be considered, but on the contrary that a
 reduction in the present 17¢ rate from the West Coast mills to Odair to
 15¢ per hundred be demanded, with a corresponding reduction in the 
rates from Eastern Washington points.
"R. F. Walter
"In dupl.
"cc: Const. Engr., Coulee Dam, Wash. "DC, Portland, Ore."
[9]  "Phoenix, Ariz. March 17, 1938 "Mr. F. R. Newman:
"Yours 9th with copy of memorandum regarding conversation with Mr. 
Clark of the Northern Pacific on matter of cement rates to Grand Coulee.
"Mr. Donnelly and I had an understanding that I thought covered the 
cement movement to Grand Coulee on everything that moves and I did not 
know there was any necessity for making a new agreement. He and I agreed
 on the rate and divisions in connection with building of road over to 
Grand Coulee Dam and I don't think there will be any misunderstanding 
regarding it.
"W. P. Kenney"